Mumbai/Project record

MahaRERA · the public record

APT PLAZA

Mumbai Suburban · APT REALCON

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

01 Aug 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

01 Aug 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800006899

Delivery and registration

When is the project declared for completion?

APT PLAZA is registered with MahaRERA as P51800006899 and the promoter has declared completion for 01 Aug 2019.

01 Aug 2019

declared completion

85months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800006899
Registered on16 Aug 2017
Promoter-declared completion01 Aug 2019
Current statusCertificate Signed
Against todayabout 85 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for APT PLAZA record 9 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 9 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Apt Realcon is the promoter of record on 76 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

76projects

registered with MahaRERA

4flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for APT PLAZA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
APT Plaza1G+13-

Legal and disputes

What disputes are disclosed?

3 complaints are on the MahaRERA record for APT PLAZA, with orders passed in 3 of them.

3complaints

3with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000005598129/08/2018Lalji Bhimji Mange vs M/s APT REALCONorder passed
CC00600000005601729/08/2018Deepak Thakker (HUF) vs APT REALCONorder passed
CC00600000005598028/08/2018Devendra S. Bhanushali vs APT REALCONorder passed

Location, Land & Connectivity

Located at Kurla, Mumbai Suburban, 400080. Per the filed land record, the plot is bounded to the north by Dharaj Apartment CTS No 787 pt C, to the south by J Dossa Shopping Centre CTS No 787, to the east by Jattashankar Dossa Road and to the west by CTS No 786 J Dossa Associated road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Powai / Hiranandani business park8 km
Andheri MIDC / SEEPZ9 km
Chhatrapati Shivaji Int'l Airport13 km
Bandra Kurla Complex (BKC)14 km
Lower Parel / Worli business district23 km
Nariman Point / Fort30 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mulund West

AAI Satidevi Paradise
possession by Sep 2026 · Shreenath Developers
Laizer Elegance
Not filing quarterly progress reports · possession by Sep 2026 · Laizer Builders & Developers
THE NEW Anand Deep CHS LTD
possession by Sep 2026 · Shreejee Buildcon
Tirupati Apartments Chsl
possession by Oct 2026 · Tirupati Aparmtnets CO Operative Housing
Horizon Garden View
possession by Nov 2026 · Horizon Promoters India LTD
Montana Phase - 3
possession by Dec 2026 · Lohitka Properties LLP

Major developers building in Mulund West

Other RERA-registered projects in Mumbai Suburban

Apurva Vaishali Chsl
declared completion Sep 2025 · Diravya Developers LLP
Aqsa Palace CHS LTD
declared completion Dec 2019 · K T Group
Aquarose
possession by Dec 2027 · Aquarock Buildcon Private Limited
Aquina
possession by Dec 2027 · Rajiv Construction Company Developers
Aranya The Park
possession by Dec 2027 · Anuradha Real Estate Developers Pvt Ltd
Arave
possession by Dec 2028 · JRT Realty LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026