Mumbai/Project record

MahaRERA · the public record

Enigma Towers A and B

Mulund · Oberoi Constructions Limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

01 Aug 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

01 Aug 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800002656

Delivery and registration

When is the project declared for completion?

Enigma Towers A and B is registered with MahaRERA as P51800002656 and the promoter has declared completion for 01 Aug 2024.

01 Aug 2024

declared completion

25months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800002656
Registered on02 Aug 2017
Promoter-declared completion01 Aug 2024
Current statusCertificate Signed
Against todayabout 25 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Enigma Towers A and B record 29 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 29 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Oberoi Constructions Limited is the promoter of record on 12 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

12projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Enigma Towers A and B in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+80.

BuildingWingsFloorsDeclared completion
Tower A1G+80-
Tower B1G+80-

Legal and disputes

What disputes are disclosed?

13 complaints are on the MahaRERA record for Enigma Towers A and B, with orders passed in 13 of them.

13complaints

13with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000000142407/11/2017RAJEEV KUMAR vs OBEROI CONSTRUCTION LIMITEDorder passed
CC00600000020990103/02/2022RAJEEV KUMAR vs OBEROI CONSTRUCTIONS LTD.order passed
CC00600000001232006/12/2017Oberoi Constructions Limited vs Asset Auto (I ) Private Limitedorder passed
CC00600000004399904/04/2018Oberoi Construction Limited vs Asset Auto (I) Private Limitedorder passed
CC00600000002332612/02/2018ASSET AUTO INDIA PVT. LTD. vs OBEROI CONSTRUCTIONS LIMITEDorder passed
CC00600000005455918/05/2018ASSET AUTO INDIA PVT LTD vs OBEROI CONSTRUCTIONS LIMITEDorder passed
CC00600000004406409/04/2018Sunil kutty Menon vs Oberoi Constructionsorder passed
CC00600000022073008/04/2022Narayan Ramratan Bubna vs Oberoi Constructions Limitedorder passed
CC00600000033409025/01/2023Krishna R Thakkar vs Oberoi Constructions Ltd Coorder passed
CC00600000039689418/08/2023Jayamadhavan Sivashankar vs Oberoi Constructions Limitedorder passed
CC00600000040858621/12/2023Reshma Bhavin Pujara vs Oberoi Construction limitedorder passed
CC00600000048030925/05/2024Sarita Rakesh Bhattar vs Oberoi Constructions Ltd.order passed
CC00600000059139712/08/2024Oberoi Realty Limited vs Rajeev Kumar and Anrorder passed

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Metropolitan Magistrate Court, 27Th Court At MulundSW/82/20222022Ongoing
Metropolitan Magistrate Court, 42Nd Court At Shindewadi, DadarPS/3/20222022Ongoing

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2023a. On account of the Covid 19 pandemic and the ensuing lockdown, the supply chains and logistics were disrupted, as a consequence whereof, supply of material, equipment and machine
30 Dec 202301 Aug 2024Once the lockdown was relaxed around August, 2020 kickstarting construction work immediately was a challenge due to reverse migration of labourers during the lockdown. The restric

Location, Land & Connectivity

Located at Mulund, LBS Marg, Borivali, Mumbai Suburban, 400080. Per the filed land record, the plot is bounded to the north by CTS No 475pt of Village Mulund, to the south by CTS No 475pt of Village Mulund, to the east by CTS No 475pt of Village Mulund and to the west by CTS No 475pt of Village Mulund. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Powai / Hiranandani business park7 km
Andheri MIDC / SEEPZ9 km
Chhatrapati Shivaji Int'l Airport12 km
Bandra Kurla Complex (BKC)14 km
Lower Parel / Worli business district23 km
Nariman Point / Fort30 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Oberoi Realty Limited is the promoter on 4 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Oberoi Realty Limited project & its RERA track record →

Other flagged projects by Oberoi Realty Limited

Oberoi Realty Limited
FlaggedMumbai Suburban
Oberoi Realty Limited
FlaggedMumbai Suburban
Oberoi Realty Limited
FlaggedMumbai Suburban
Oberoi Realty Limited
FlaggedMumbai Suburban
Oberoi Realty Limited
FlaggedThane
Oberoi Realty Limited
FlaggedMumbai Suburban

Other RERA-registered projects in Mulund West

AAI Satidevi Paradise
possession by Sep 2026 · Shreenath Developers
Laizer Elegance
Not filing quarterly progress reports · possession by Sep 2026 · Laizer Builders & Developers
THE NEW Anand Deep CHS LTD
possession by Sep 2026 · Shreejee Buildcon
Tirupati Apartments Chsl
possession by Oct 2026 · Tirupati Aparmtnets CO Operative Housing
Horizon Garden View
possession by Nov 2026 · Horizon Promoters India LTD
Montana Phase - 3
possession by Dec 2026 · Lohitka Properties LLP

Major developers building in Mulund West

Other RERA-registered projects in Mumbai Suburban

Enso Sanza
declared completion Jun 2026 · Sai Aastha Developers
Enterprise ONE
possession by Dec 2030 · EVO Borivali LLP
Epitome
declared completion Dec 2025 · Thoroughbred Realty LLP
Espinal
declared completion Dec 2018 · Punit Buildcon PVT LTD
Esquina Private Residence
possession by Jun 2029 · Prabhakar Kunte CO Operative Housing Soc
Esspee Tower
possession by Jul 2027 · Bhatia Builders AND Developers PVT LTD

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026