Runwal Pinnacle

Mulund(West) · Runwal Enterprises Limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2028declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800021322

Delivery and registration

When is the project declared for completion?

Runwal Pinnacle is registered with MahaRERA as P51800021322 and the promoter has declared completion for 30 Dec 2028.

30 Dec 2028

declared completion

27months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800021322
Registered on21 Jun 2019
Promoter-declared completion30 Dec 2028
Current statusCertificate Signed
Against today27 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Runwal Pinnacle record 28 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 28 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Runwal Enterprises Limited is the promoter of record on 57 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

57projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In Runwal Pinnacle, ₹312.39 Cr of a declared ₹717.72 Cr estimated project cost is reported as incurred, about 43.5%, as at the last certified filing with MahaRERA.

43.5%

₹312.39 Cr

of ₹717.72 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Runwal Pinnacle in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+56.

BuildingWingsFloorsDeclared completion
Tower 11G+56-
Tower 21G+56-
Tower 31G+56-
Tower 41G+56-
Tower 51G+56-

Legal and disputes

What disputes are disclosed?

8 complaints are on the MahaRERA record for Runwal Pinnacle, with orders passed in 3 of them.

8complaints

3with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000037482917/03/2023Umesh Baban Korade vs Runwal Pinnacleorder passed
CC00600000042955208/03/2024SAGAR PHAPALE vs RUNWAL APARTMENT PRIVATE LIMITEDorder passed
CC1250052815/02/2025Cajetan Pereira vs Runwal Apartments Private Limitedorder passed
CC1250176229/05/2025Sandeep Anil Kudva vs Runwal Apartments Private Limitedpending / no order on file
CC1250375627/10/2025Runwal Enterprises Limited vs Nanda Pravin Magdumpending / no order on file
CC1250389907/11/2025Runwal Enterprises Limited vs Aruna Madhukar Dahiwalpending / no order on file
CC1250452618/12/2025Runwal Enterprises Limited vs Mohd Saleempending / no order on file
CC1260427007/07/2026HEMANT UTTAM BANSODE vs Runwal Enterprises Limitedpending / no order on file

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
City Civil Court BombayLC Suit No 100552/20132013Disposed Off

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2027Project completion has been delayed due to certain mitigating circumstances beyond the control of the Promoter
30 Jun 202730 Dec 2028The delay in completion of the Project has occurred due to post-pandemic disruptions, unanticipated site conditions such as hard rock strata requiring controlled blasting, and dela

Location, Land & Connectivity

Located at Mulund(West), Goregaon Mulund Link Road, Mumbai City, Mumbai City, 400080. Per the filed land record, the plot is bounded to the north by Fortis Hospital, to the south by CTS No 767 and 768, to the east by Residential Towers and to the west by Hospital reservation. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Powai / Hiranandani business park6 km
Andheri MIDC / SEEPZ9 km
Chhatrapati Shivaji Int'l Airport11 km
Bandra Kurla Complex (BKC)13 km
Lower Parel / Worli business district22 km
Nariman Point / Fort29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mulund West

AAI Satidevi Paradise
possession by Sep 2026 · Shreenath Developers
Laizer Elegance
Not filing quarterly progress reports · possession by Sep 2026 · Laizer Builders & Developers
THE NEW Anand Deep CHS LTD
possession by Sep 2026 · Shreejee Buildcon
Tirupati Apartments Chsl
possession by Oct 2026 · Tirupati Aparmtnets CO Operative Housing
Horizon Garden View
possession by Nov 2026 · Horizon Promoters India LTD
Montana Phase - 3
possession by Dec 2026 · Lohitka Properties LLP

Major developers building in Mulund West

Other RERA-registered projects in Mumbai Suburban

Runwal R-Square
declared completion Mar 2024 · Runwal Developers Ltd
Runwal Serene
declared completion May 2019 · Runwal Construction Private Limited
Runwal Westwind Heights
possession by Dec 2028 · Ariane Orgachem Private Limited
Runwal Woods
possession by Sep 2028 · Evie Holdings Private Limited And Adisha
Ruparel Arista
possession by Mar 2028 · R R Builders
Ruparel Celestia
possession by Dec 2026 · Aadarsh Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026