MahaRERA Property Intelligence · Mumbai Suburban

AQSA PALACE CHS LTD

P51800003447 · promoter Group

Certificate SignedDue 31 Dec 2019

Delivery & Registration

MahaRERA registrationP51800003447
Registered on05 Aug 2017
Promoter-declared completion31 Dec 2019
Current statusCertificate Signed
Against todayabout 79 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.

BuildingWingsFloorsDeclared completion
AQSA PALACE CHS LTD1G+12-

Complaints & Orders

2 complaints are on the MahaRERA record for this project, with orders passed in 2. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000004450415/05/2018Ayazuddin ansari vs K T GROUPorder passed
CC00600000019325902/06/2020Nyra Ann Mendonca vs Sandeep Sethorder passed

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 400064. Per the filed land record, the plot is bounded to the north by CTS 45, to the south by DOMINIC COLONY ROAD 3, to the east by 6M WIDE ACCESS and to the west by CTS 43. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ7 km
Powai / Hiranandani business park10 km
Chhatrapati Shivaji Int'l Airport11 km
Bandra Kurla Complex (BKC)14 km
Lower Parel / Worli business district21 km
Nariman Point / Fort29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

K T Group is the promoter on 6 MahaRERA-registered projects, of which 6 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by K T Group

K T Group
Past its declared completion dateMumbai Suburban
K T Group
Past its declared completion dateMumbai Suburban
K T Group
Past its declared completion dateMumbai Suburban
K T Group
Past its declared completion dateMumbai Suburban
K T Group
Past its declared completion dateMumbai Suburban

Other RERA-registered projects in Malad West

Ajmera Arham
possession by Jul 2026 · Vishal Construction
Imperial Hava Hira
possession by Jul 2026 · Shree SAI Realty
Liberte64
possession by Aug 2026 · Jadhwani Infrastructure LLP
Ramdev Veeral Heights
possession by Aug 2026 · Ramdev Associates
Rajgopal Building
possession by Sep 2026 · Harmony AND Prosperity Developer
Shree Hari Krupa
possession by Sep 2026 · Mamtora Foundation

Major developers building in Malad West

Other RERA-registered projects in Mumbai Suburban

Aquaria Grande, Wing B Floor 33-38
declared completion Dec 2021 · Club Aquaria Enterprises
Aquarose
possession by Dec 2027 · Aquarock Buildcon Private Limited
Aquina
possession by Dec 2027 · Rajiv Construction Company Developers
Aranya The Park
possession by Dec 2027 · Anuradha Real Estate Developers Pvt Ltd
Arave
possession by Dec 2028 · JRT Realty LLP
Arbuda Darshan CHS LTD
declared completion Dec 2023 · Supreme Realtors

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.