Mumbai/Project record

MahaRERA · the public record

SAI VISHAL CHS LTD

Mumbai Suburban · K T GROUP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800008567

Delivery and registration

When is the project declared for completion?

SAI VISHAL CHS LTD is registered with MahaRERA as P51800008567 and the promoter has declared completion for 31 Dec 2019.

31 Dec 2019

declared completion

81months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800008567
Registered on19 Aug 2017
Promoter-declared completion31 Dec 2019
Current statusCertificate Signed
Against todayabout 81 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SAI VISHAL CHS LTD record 10 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 10 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SAI VISHAL CHS LTD in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
SAI VISHAL CHSL1G+15-

Legal and disputes

What disputes are disclosed?

11 complaints are on the MahaRERA record for SAI VISHAL CHS LTD, with orders passed in 11 of them.

11complaints

11with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000001276405/02/2018Pranav Joshi vs K.T Grouporder passed
CC00600000005755407/01/2019Pranav Shantilal Joshi and Shantilal Narayandas Joshi vs M/s. K.T. Group through their partners Sandeep K. Seth and Dhairya K. Sethorder passed
CC00600000002300009/05/2018Jaya Ankur Singhania vs KT GROUP & Their partnersorder passed
CC00600000004449823/05/2018Sudhir B Sharma vs KT GROUP & THEIR PARTNERSorder passed
CC00600000005462423/05/2018Sudhir B Sharma & Pravesh Sudhir Sharma vs KT GROUP & PARTNERSorder passed
CC00600000002373219/03/2018Mrs. Nirmala Rao vs M/s. KT Group through its partner Mr. Sandeep Shethorder passed
CC00600000002373319/03/2018Rahul Rajesh Sharma and Rohit Rajesh Sharma vs M/s. KT Group though its partner Mr. Sandeep Shethorder passed
CC00600000004442816/05/2018Ritika Tarun Kohli and Tarun Udesh Kohli vs M/s. KT Group through its partner Mr. Dhairya sheth & Mr. Sandeep Shethorder passed
CC00600000005480406/06/2018Jetharam Devaram Patel vs M/S K T GROUPorder passed
CC00600000005501127/06/2018Mr. Hareshbhai Narshibhai Damania vs M/s KT Group through partner Sandeep Shethorder passed
CC00600000007948327/05/2019SAI VISHAL CHSL (society) vs K T GROUPorder passed

A co-operative housing society is recorded as the complainant (SAI VISHAL CHSL), and MahaRERA has passed an order.

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 400064. Per the filed land record, the plot is bounded to the north by SAI AMIT CHSL, to the south by JYOTI CASTLE CHSL, to the east by SAI BABA PARK GARDEN and to the west by OPEN ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ7 km
Powai / Hiranandani business park10 km
Chhatrapati Shivaji Int'l Airport11 km
Bandra Kurla Complex (BKC)14 km
Lower Parel / Worli business district21 km
Nariman Point / Fort29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

K T Group is the promoter on 6 MahaRERA-registered projects, of which 6 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by K T Group

K T Group
Past its declared completion dateMumbai Suburban
K T Group
Past its declared completion dateMumbai Suburban
K T Group
Past its declared completion dateMumbai Suburban
K T Group
Past its declared completion dateMumbai Suburban
K T Group
Past its declared completion dateMumbai Suburban

Other RERA-registered projects in Malad West

Shree Hari Krupa
possession by Sep 2026 · Mamtora Foundation
Shreeji Plaza Wing B
possession by Sep 2026 · Siddharth Enterprises
Linkpark
possession by Oct 2026 · Adarsh Industrial Estate Private Limited
Bhagat Grandeur
possession by Dec 2026 · Chirag Agro Fins Private Limited
Liberty Heights
possession by Dec 2026 · VP Casa Constructions LLP
Lovely Chs. LTD
possession by Dec 2026 · Jinam Realtors

Major developers building in Malad West

Other RERA-registered projects in Mumbai Suburban

Sainath Malad SRA CHS
declared completion Dec 2017 · Shree Mahalaxmi Associates
Sainath Residency
possession by Dec 2026 · Sainath Buildcon
Sairah
declared completion Jun 2019 · Metro Associates
Sajag CHS
declared completion Dec 2020 · Navkar Infra Projects
Sajay Avenue 18
declared completion Aug 2026 · Vinca Realtors Private Limited
Sajay Avenue 92
possession by Jun 2028 · Sajay Developer

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.