31 May 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 May 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800006904

Delivery and registration

When is the project declared for completion?

BORIVALI SANGRAM CHS LTD is registered with MahaRERA as P51800006904 and the promoter has declared completion for 31 May 2019.

31 May 2019

declared completion

88months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800006904
Registered on16 Aug 2017
Promoter-declared completion31 May 2019
Current statusCertificate Signed
Against todayabout 88 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for BORIVALI SANGRAM CHS LTD record 8 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 8 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for BORIVALI SANGRAM CHS LTD in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16.

BuildingWingsFloorsDeclared completion
BORIVALI SANGRAM CHS LTD1G+16-

Legal and disputes

What disputes are disclosed?

7 complaints are on the MahaRERA record for BORIVALI SANGRAM CHS LTD, with orders passed in 7 of them.

7complaints

7with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000000038408/02/2018Neha Amey Kolhatkar and Amey Girish Kolhatkar vs M/s K.T. Grouporder passed
CC00600000005474324/06/2018ONKAR ASHOK SAWANT, ASHOK BALKRISHNA SAWANT vs Sandeep Sheth KT Grouporder passed
CC00600000000098305/10/2017D. B. Puthran vs K T Grouporder passed
CC00600000005497017/06/2018JAYRAJ GOKHALE vs K T GROUPorder passed
CC00600000005462517/06/2018Dr Prashant S Mahajan vs KT Grouporder passed
CC00600000005587828/08/2018Kejal Bang vs K T Group through its Partnersorder passed
CC00600000008967010/06/2019SHITAL BHAUTIK SHAH AND BHAUTIKVINODKUMAR SHAH vs K. T. GROUPorder passed

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 400092. Per the filed land record, the plot is bounded to the north by CTS 2108, to the south by CTS 2174 AND 2171, to the east by CTS NO 2176 and to the west by CTS NO 2108. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~12 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ12 km
Powai / Hiranandani business park15 km
Chhatrapati Shivaji Int'l Airport16 km
Bandra Kurla Complex (BKC)19 km
Lower Parel / Worli business district27 km
Nariman Point / Fort35 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

K T Group is the promoter on 6 MahaRERA-registered projects, of which 6 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by K T Group

K T Group
Past its declared completion dateMumbai Suburban
K T Group
Past its declared completion dateMumbai Suburban
K T Group
Past its declared completion dateMumbai Suburban
K T Group
Past its declared completion dateMumbai Suburban
K T Group
Past its declared completion dateMumbai Suburban

Other RERA-registered projects in Borivali West

Gopal Terrace Co-Operative Housing Society LTD
possession by Sep 2026 · Polo Infra Developers Private Limited
House Of Shreeji Sharan
possession by Sep 2026 · Miles Infra LLP
Sai Signature Spaces
possession by Sep 2026 · Ramachandran Munisawmy Narayan
Shikhhar
possession by Sep 2026 · Mahavir Land Developer
Swastik
possession by Sep 2026 · Reliance Corporation
Signet
possession by Oct 2026 · DG Builders

Major developers building in Borivali West

Other RERA-registered projects in Mumbai Suburban

Borivali Shalimar CO-Operative Housing Society Limited
declared completion Dec 2024 · Tasmai Shree
Borivali Shanti Krupa Chsl
declared completion Dec 2025 · Namo Shreen Ventures LLP
Borivali Shiv Sadan Chsl
possession by Oct 2027 · Ossia Developers
Borivali Vardhman Darshan Chsl
declared completion May 2024 · Shri Neelkanth Developers
Borivali Veer Dhaval
declared completion May 2026 · Shree Durga Vastu Makers LLP
Borivali Yashodhan Chsl
declared completion Jun 2025 · TGN Realtor LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026