MahaRERA · the public record

Apna Ghar Phase III

Village Ghodbunder, MIra Bhayandar road , MIra ROad East · Seven Eleven Construction Private Limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Mar 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700016020

Delivery and registration

When is the project declared for completion?

Apna Ghar Phase III is registered with MahaRERA as P51700016020 and the promoter has declared completion for 31 Mar 2025.

31 Mar 2025

declared completion

18months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700016020
Registered on12 Apr 2018
Promoter-declared completion31 Mar 2025
Current statusCertificate Signed
Against todayabout 18 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Apna Ghar Phase III record 28 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Filing progress reports — 28 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Seven Eleven Construction is the promoter of record on 9 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

9projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Apna Ghar Phase III in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+22.

BuildingWingsFloorsDeclared completion
A11G+2231 Dec 2021
A21G+2231 Dec 2021
A31G+2231 Dec 2021
A41G+2231 Dec 2021
B11G+2231 Dec 2021
B21G+2231 Dec 2021
B31G+2231 Dec 2021
C31G+2231 Dec 2021
C41G+2231 Dec 2021
Shopping Complex1G+131 Dec 2021
Bunglow 11G+231 Dec 2021
Bunglow 21G+131 Dec 2021
Bunglow 31G+231 Dec 2021

Legal and disputes

What disputes are disclosed?

3 complaints are on the MahaRERA record for Apna Ghar Phase III, with orders passed in 1 of them.

3complaints

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000042909623/02/2024Jayram sharma vs Seven Eleven Construction Pvt. Ltd.order passed
CC1250086712/03/2025Sonal Ravindra Tambe vs Seven Eleven Construction Private Limitedpending / no order on file
CC1250095418/03/2025Sham Himmatsingh Kowor vs Seven Eleven Construction Private Limitedpending / no order on file

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered20 Dec 2023DUE TO NON AVAILABILITY OF CEMENT AND DUE TO DELAY IN SOME PERMISSION, WE WERE NOT ABLE TO COMPLETE THE PROJECT IN TIME, THEREFORE WE WOULD REQUEST YOU TO PLEASE GRANT US THE CERTI
20 Dec 202331 Aug 2024The Applicant has submitted to the planning Authority all the documents and papers for obtaining occupation certificate. The said planning authority till date has not issued the o
31 Aug 202431 Mar 2025WE WOULD LIKE TO INFORM YOU THAT WE HAVE ALREADY APPLIED FOR OCCUPATION CERTIFICATE. THE PLANNING AUTHORITY I.E. MIRA BHAYANDAR MUNICIPAL CORPORATION HAS RAISED CERTAIN QUERIES PRI

Location, Land & Connectivity

Located at Village Ghodbunder, MIra Bhayandar road , MIra ROad East, Behind Jhankar Company, Near Vinay Nagar, Thane, Thane, 401107. Per the filed land record, the plot is bounded to the north by Survey number 221, to the south by Survey number 220, to the east by Survey number 147 and to the west by Survey number 140 and survey number 220. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~17 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ17 km
Powai / Hiranandani business park18 km
Chhatrapati Shivaji Int'l Airport21 km
Bandra Kurla Complex (BKC)24 km
Lower Parel / Worli business district32 km
Nariman Point / Fort40 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Seven Eleven Construction Private Limited is the promoter on 5 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Seven Eleven Construction Private Limited project & its RERA track record →

Other RERA-registered projects in Mira Road East

Beaumonde
possession by Sep 2026 · Kanungo Property
Rassaz Greens Tower C D AND E
possession by Dec 2026 · Rassaz Infrastructure Private Limited
Coral
Deregistered by MahaRERA · possession by Dec 2026 · Nilesh Shantilal Tank
JP North Aviva
possession by Dec 2026 · JP Infra Realty Private Limited
Prithvi Sneh
Deregistered by MahaRERA · possession by Dec 2026 · Prithvi Buildworth Constructions
Shree RAM Heights
possession by Dec 2026 · Vavya Enterprises

Major developers building in Mira Road East

Other RERA-registered projects in Thane

Apna Ghar Phase III NX
possession by Mar 2027 · Seven Eleven Construction Pvt Ltd
APR Realty Crown
possession by Dec 2027 · APR Realty
Aqua Abode
declared completion Dec 2024 · Jainam Developers
Aradhana
declared completion Dec 2019 · Simran Infrastructures
Aravali
declared completion Sep 2024 · Singh Construction
Arbisha Apartment
possession by Dec 2032 · Arbisha Construction

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026