MahaRERA · the public record
ARIHANT ALOKI PHASE V
karjat · ARIHANT AASHIYANA PRIVATE LIMITED
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
31 Dec 2031
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P52000025052
Delivery and registration
When is the project declared for completion?
ARIHANT ALOKI PHASE V is registered with MahaRERA as P52000025052 and the promoter has declared completion for 31 Dec 2031.
31 Dec 2031
declared completion
63months to go
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P52000025052 |
| Registered on | 18 Mar 2020 |
| Promoter-declared completion | 31 Dec 2031 |
| Current status | Certificate Signed |
| Against today | 63 months to the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ARIHANT ALOKI PHASE V record 25 quarterly progress reports since registration.
25quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Filing progress reports — 25 quarterly progress reports on record since registration, with no current default.
Promoter record
What else is this promoter on record for?
Arihant Aashiyana is the promoter of record on 15 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
15projects
registered with MahaRERA
0flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Construction
How much construction cost has been reported?
In ARIHANT ALOKI PHASE V, ₹0 of a declared ₹20.77 Cr estimated project cost is reported as incurred, about 0.0%, as at the last certified filing with MahaRERA.
0.0%
₹0
of ₹20.77 Cr declared cost
Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.
Source · MahaRERA quarterly progress filing · read 12 Jul 2026
Sales
How much has actually been sold?
In ARIHANT ALOKI PHASE V, 0 of 142 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 142 remain available.
0%sold
0 of 142 homes
Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.
Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for ARIHANT ALOKI PHASE V in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 18 September 2026
What the filings record, home by home
Read from MahaRERA on 18 September 2026
No home in ARIHANT ALOKI PHASE V carries a registered agreement value on its MahaRERA filing, so there is no record here of what anyone has paid. What the promoter has filed is the government ready reckoner value for 142 homes — the Annual Statement of Rates valuation, with each home’s carpet area and floor already applied. Across them that is Rs 3,958 a sq ft typical, over Rs 3,958 to Rs 3,958.
A reckoner value is the basis stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home to you.
The Reckoner Record lists all 142 of them — each home, its RERA carpet area, the valuation filed against it and the rate that works out to. It is the filing copied, not a reading of it.
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16 and 142 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| C1 | 1 | G+16 | 142 | - |
Unit mix on the filing: 142 residential.
Legal and disputes
What disputes are disclosed?
1 complaint is on the MahaRERA record for ARIHANT ALOKI PHASE V, with orders passed in 1 of them.
1complaint
1with an order
Counts as disclosed in the project record.
Source · MahaRERA project disclosures · read 12 Jul 2026
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| SM12600110 | 05/02/2026 | Bhakti Achrekar vs ARIHANT AASHIYANA PRIVATE LIMITED | order passed |
Legal & Litigation
The promoter has declared 2 court cases on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.
| Court | Case no. | Year | Status |
|---|---|---|---|
| Court Of Civil Judge Karjat | RCS No 120/2018 | 2018 | Pending For Hearing On Application For Dismissal Of Suit |
| Civil Judge Junior Division | 120/2018 | 2018 | Ongoing |
Deadline Extensions
The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.
| From | Extended to | Stated reason |
|---|---|---|
| as registered | 31 Dec 2031 | In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various r |
Location, Land & Connectivity
Located at karjat, Bhisegaon, Thane, Thane, 410201. Per the filed land record, the plot is bounded to the north by 12 METER WIDE D P ROAD, to the south by MAUJE KARJATVILLAGE BOUNDRY, to the east by MSRDC and to the west by HISSA NO-32. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~49 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.
| Landmark | Straight-line |
|---|---|
| Powai / Hiranandani business park | 49 km |
| Bandra Kurla Complex (BKC) | 50 km |
| Chhatrapati Shivaji Int'l Airport | 51 km |
| Nariman Point / Fort | 52 km |
| Lower Parel / Worli business district | 52 km |
| Andheri MIDC / SEEPZ | 53 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.