ARIHANT ALOKI PHASE VI

Bhisegaon · ARIHANT AASHIYANA PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

174units filed as unsoldInventory · 18 September 2026
31 Dec 2031declared completionMahaRERA registration · read 12 Jul 2026
174registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2031

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000025180

Delivery and registration

When is the project declared for completion?

ARIHANT ALOKI PHASE VI is registered with MahaRERA as P52000025180 and the promoter has declared completion for 31 Dec 2031.

31 Dec 2031

declared completion

63months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000025180
Registered on20 Mar 2020
Promoter-declared completion31 Dec 2031
Current statusCertificate Signed
Against today63 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ARIHANT ALOKI PHASE VI record 25 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 25 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Arihant Aashiyana is the promoter of record on 15 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

15projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In ARIHANT ALOKI PHASE VI, ₹0 of a declared ₹25.69 Cr estimated project cost is reported as incurred, about 0.0%, as at the last certified filing with MahaRERA.

0.0%

₹0

of ₹25.69 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In ARIHANT ALOKI PHASE VI, 0 of 174 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 174 remain available.

0%sold

0 of 174 homes

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ARIHANT ALOKI PHASE VI in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 September 2026

What the filings record, home by home

Read from MahaRERA on 18 September 2026

No home in ARIHANT ALOKI PHASE VI carries a registered agreement value on its MahaRERA filing, so there is no record here of what anyone has paid. What the promoter has filed is the government ready reckoner value for 174 homes — the Annual Statement of Rates valuation, with each home’s carpet area and floor already applied. Across them that is Rs 3,781 a sq ft typical, over Rs 3,781 to Rs 3,781.

A reckoner value is the basis stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home to you.

The Reckoner Record lists all 174 of them — each home, its RERA carpet area, the valuation filed against it and the rate that works out to. It is the filing copied, not a reading of it.

See all 174 filed valuations — ₹999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16 and 174 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
C21G+16174-

Unit mix on the filing: 174 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Court Of Civil Judge KarjatRCS No 120/20182018Pending For Hearing On Application For Dismissal Of Suit
Civil Judge Junior Division120/20182018Ongoing

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2031In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various r

Location, Land & Connectivity

Located at Bhisegaon, Bhisegaon, Thane, Thane, 410201. Per the filed land record, the plot is bounded to the north by 12 METER WIDE DP ROAD, to the south by MAUJE KARJAT VILLAGE BOUNDRY, to the east by MSRDC and to the west by HISSA NO-32. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~49 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park49 km
Bandra Kurla Complex (BKC)50 km
Chhatrapati Shivaji Int'l Airport51 km
Nariman Point / Fort52 km
Lower Parel / Worli business district52 km
Andheri MIDC / SEEPZ53 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Arihant Aashiyana Private Limited is the promoter on 12 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Arihant Aashiyana Private Limited project & its RERA track record →

Other flagged projects by Arihant Aashiyana Private Limited

Arihant Aashiyana Private Limited
FlaggedThane
Arihant Aashiyana Private Limited
FlaggedRaigarh
Arihant Aashiyana Private Limited
FlaggedRaigarh
Arihant Aashiyana Private Limited
FlaggedRaigarh
Arihant Aashiyana Private Limited
FlaggedRaigarh

Other RERA-registered projects in Karjat

Dhanlaxmi Heights
possession by Sep 2026 · Dhanlaxmi Developers
Warai Woods Ph 2
Not filing quarterly progress reports · possession by Nov 2026 · Nahar Riddhi Siddhi Developers
Jambrung Valley
possession by Nov 2026 · Kirtiraj Nanasaheb Sawant
Bliss Studio
possession by Dec 2026 · Balsam Builders
Beverly Hills
possession by Dec 2026 · Rudram Infra Projects Private Limited
Jupiter Heights
Not filing quarterly progress reports · possession by Dec 2026 · Jupiter Heights

Major developers building in Karjat

Other RERA-registered projects in Raigarh

Arihant Amisha Phase II
possession by Dec 2026 · Arihant Aashiyana Private Limited
Arihant Amisha Phase III
possession by Dec 2027 · Arihant Aashiyana Private Limited
Arihant Anaika Phase II
declared completion Dec 2023 · Arihant Vatika Realty Private Limited
Arihant Anant
possession by Dec 2026 · Mahalaxmi Cotton Mills
Arihant Anant Phase II
possession by Dec 2027 · Mahalaxmi Cotton Mills
Arihant Arshiya Phase IV
possession by Dec 2030 · Arihant Superstructures Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026