Mumbai/Project record

MahaRERA · the public record

Ascon Heights

Palghar · Murtuza Yusuf Electricwala

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000012633

Delivery and registration

When is the project declared for completion?

Ascon Heights is registered with MahaRERA as P99000012633 and the promoter has declared completion for 30 Jun 2019.

30 Jun 2019

declared completion

87months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000012633
Registered on06 Sep 2017
Promoter-declared completion30 Jun 2019
Current statusCertificate Signed
Against todayabout 87 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Ascon Heights record 8 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 8 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Ascon Heights in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+122.

BuildingWingsFloorsDeclared completion
Rose1G+122-
LILLY1G+5-
STAR1--
MOON1--
LITTLE STAR1--
LITTLE MOON1--
JASMIN1--
CHAMPA1--

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for Ascon Heights, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000023114614/05/2022Geeta Rajesh Kumar vs MUTURZA ELECTRICWALAorder passed

Location, Land & Connectivity

Located at Vasai, Palghar, 401501. Per the filed land record, the plot is bounded to the north by survey no 160 part towards north, to the south by road towards south, to the east by survey no 160 2 towards east side and to the west by plot no 1 survey no 160 2 and road towards west. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~75 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ75 km
Powai / Hiranandani business park77 km
Chhatrapati Shivaji Int'l Airport79 km
Bandra Kurla Complex (BKC)82 km
Lower Parel / Worli business district89 km
Nariman Point / Fort96 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Boisar

Classic Apartment
possession by Sep 2026 · I.k.group
Divyajal
possession by Sep 2026 · Divyaraj Properties LLP
Kinjal Complex II
possession by Sep 2026 · Kinjal Enterprises
Queens Villa - 2
possession by Sep 2026 · Super Realty
Marathe Complex
possession by Dec 2026 · Gprs Realty
Rajhans United Regency III
possession by Dec 2026 · Rajhans Homes

Other RERA-registered projects in Palghar

Ashiyana
possession by Mar 2027 · SOL Infra
Ashiyana Building NO 9
possession by Dec 2028 · North Star Ashiyana
Ashok Apartment
possession by Dec 2027 · Trishika Homes
Ashoka Heavens
possession by Dec 2026 · Shree Mahashraman Realtors
Ashoka Hills
possession by Sep 2029 · Shree Ashoka Builders & Developers
Ashoka Residency
possession by Dec 2027 · Neelima Ashok Wedhikar

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026