MahaRERA Property Intelligence · Thane

Ashapura Enclave

P51700004374 · promoter Ashapura Enterprises

Certificate SignedDue 30 Dec 2021

Delivery & Registration

MahaRERA registrationP51700004374
Registered on09 Aug 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 55 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Ashapura Enterprises is the promoter of record on 58 projects, of which 5 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
Ashapura Enclave1G+7-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202130 Dec 2020Tax assessment by Municipal Corporation is Under Process and after paying such tax completion will be issue by Municipal Corporation.

Location, Land & Connectivity

Located at Kalyan, Thane, 421202. Per the filed land record, the plot is bounded to the north by Shivsunder Park, to the south by New Sindhudurg Society, to the east by Ramchandra Complex and to the west by Property of Shri Rajendra P Mhatre. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~22 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park22 km
Andheri MIDC / SEEPZ24 km
Chhatrapati Shivaji Int'l Airport27 km
Bandra Kurla Complex (BKC)28 km
Lower Parel / Worli business district36 km
Nariman Point / Fort42 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Palava

Evaan
possession by Jul 2026 · Impressions NXT
Saraswati Devi Krupa
possession by Jul 2026 · Yogiraj Heritage
JAI Malhar Plaza
possession by Aug 2026 · Swaminarayan Residency
Amar Elegance
possession by Sep 2026 · Amar Realty
Purva Prime
possession by Sep 2026 · Trimurti Constructions
Anant AND Radhika Heights
possession by Dec 2026 · Ashapura Construction CO

Major developers building in Palava

Other RERA-registered projects in Thane

Ashapura Galaxy
possession by Mar 2027 · Ashapura Estates
Ashapura Galaxy
possession by Jun 2028 · S R Enterprises
Ashapura Gold
possession by Dec 2027 · Ashapura Buildtech
Ashapura Prasad
declared completion Jun 2022 · Ashapura Nirman Developers
Ashapura Riddhi Tower
possession by Dec 2029 · Sanjaykumar Makanji Kotak Thakkar
Ashapura Royal
declared completion Jun 2025 · Gayatri Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026