Asma Enclave

Kurla West · FAITH K S INFRA LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2029declared completionMahaRERA registration · read 02 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 02 Jul 2026

The record · free to read

Registration read 02 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2029

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 02 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · PR1180002600996

Delivery and registration

When is the project declared for completion?

Asma Enclave is registered with MahaRERA as PR1180002600996 and the promoter has declared completion for 31 Dec 2029.

31 Dec 2029

declared completion

39months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 02 Jul 2026

MahaRERA registrationPR1180002600996
Registered on30 Jun 2026
Promoter-declared completion31 Dec 2029
Current statusCertificate Signed
Against today39 months to the declared date

Promoter record

What else is this promoter on record for?

Faith Infra Llp is the promoter of record on 8 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

8projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 02 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Asma Enclave in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 02 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16.

BuildingWingsFloorsDeclared completion
Asma Enclave1G+16-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Kurla West, M. Patankar Road, Mumbai City, Mumbai City, 400070. Per the filed land record, the plot is bounded to the north by CTS No. 632, to the south by Pipe line Road, to the east by CTS No. 629 & 630 and to the west by B.M.C Road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~1 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)1 km
Chhatrapati Shivaji Int'l Airport3 km
Powai / Hiranandani business park6 km
Andheri MIDC / SEEPZ7 km
Lower Parel / Worli business district9 km
Nariman Point / Fort17 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kurla West

Yojan One
possession by Sep 2026 · Meru Realty LLP
Imperial Heights
possession by Nov 2026 · Sumukha Realtors
Buddha Vihar CHS LTD
possession by Dec 2026 · M/S Regal Builders AND Developers
Khaliliya Complex
possession by Dec 2026 · Dani Builders AND Developers
Mantri Business Plaza
possession by Dec 2026 · Mantri Brothers
Rehmaniya Apartments
possession by Dec 2026 · S & S Enterprises

Major developers building in Kurla West

Other RERA-registered projects in Mumbai Suburban

Asmi Business Centre
possession by Dec 2028 · Asmi Corporation
Asmi Dreamz
declared completion Dec 2024 · Ajay Malshi Dedhia
Asmi Garden
declared completion Jun 2024 · Rajesh Malshi Dedhia
Asmi Legacy
possession by Dec 2026 · Asmi Developers
Asmi Legend
possession by Dec 2027 · Angel Construction Company
Asmi Shimmers
declared completion Dec 2025 · Ajay Malshi Dedhia

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 18 Sep 2026