Mumbai/Project record

MahaRERA · the public record

ATHARV OM CHANDRAMILAN

VILEPARLE EAST · ATHARV INFRA LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

0units filed as unsoldInventory · 19 September 2026
31 Dec 2028declared completionMahaRERA registration · read 12 Jul 2026
44registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800054052

Delivery and registration

When is the project declared for completion?

ATHARV OM CHANDRAMILAN is registered with MahaRERA as P51800054052 and the promoter has declared completion for 31 Dec 2028.

31 Dec 2028

declared completion

27months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800054052
Registered on27 Dec 2023
Promoter-declared completion31 Dec 2028
Current statusCertificate Signed
Against today27 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ATHARV OM CHANDRAMILAN record 6 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 6 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Atharv Infra Llp is the promoter of record on 117 projects registered with MahaRERA, 14 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

117projects

registered with MahaRERA

14flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In ATHARV OM CHANDRAMILAN, ₹23.08 Cr of a declared ₹27.14 Cr estimated project cost is reported as incurred, about 85.0%, as at the last certified filing with MahaRERA.

85.0%

₹23.08 Cr

of ₹27.14 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In ATHARV OM CHANDRAMILAN, 10 of 10 homes filed with MahaRERA are recorded as sold or booked, about 100%, and 0 remain available.

100%sold

10 of 10 homes

₹67.63 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹59.75 Cr (about 88%) is recorded as collected and ₹7.87 Cr as receivable. The project registers 44 homes in total, while this sold/unsold inventory filing covers 10 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 10 registered agreements, the effective carpet rate is ₹33,001/sqft, with eight in ten falling between ₹25,001 and ₹39,929 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 19 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 10 homes carry one, and Every home on the filing is recorded sold or booked.

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

Every home in ATHARV OM CHANDRAMILAN is filed sold or booked, so there is no asking price left to test — but the record of what this project sold for is complete. The Price Comparison Report lists all 10 registered agreements: each home, its carpet area, the consideration filed against it and the rate that works out to. Built from the filing itself, sent by email.

See all 10 registered agreements — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11 and 44 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
ATHARV OM CHANDRA MILAN-WING-A1G+1014-
ATHARV OM CHANDRA MILAN-WING B1G+1130-

Unit mix on the filing: 44 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at VILEPARLE EAST, VILEPARLE, Andheri, Mumbai Suburban, 400057. Per the filed land record, the plot is bounded to the north by cts no 582, to the south by cts no 585 and 586, to the east by Existing 18 30 mts wide MG road and to the west by existing road 9 mtr wide. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Vile Parle East

Moti Madhav
possession by Sep 2026 · Aadhya Skyvista
Neumec Niwara
possession by Sep 2026 · Neumec Venture
Yeshwant Sadan
possession by Sep 2026 · ARG Life Spaces LLP
Vile Parle Mamata Chsl
possession by Oct 2026 · Dhruv Infrastructure
Vanmala Nivas CHS LTD
possession by Nov 2026 · AMI Infra Realtors
ZEE Nayak
possession by Dec 2026 · Pragatee ZEE

Other RERA-registered projects in Mumbai Suburban

Atharv Pride
declared completion Dec 2024 · Atharv Realty Buildcon LLP
Atharv Shagun
declared completion Dec 2021 · M/S Atharv Realty
Atharva
possession by Mar 2027 · Maya Developers
Atharva Complex
declared completion Jun 2024 · Atharva Realtors
Atharva Vaibhav
possession by Dec 2028 · Atharva Developers
Athena
declared completion Jan 2024 · Not Available

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026