MahaRERA · the public record
Avanti Heights
Virar west · Pramod Ramesh Bhandavalkar
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
31 Dec 2029
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P99000078228
Delivery and registration
When is the project declared for completion?
Avanti Heights is registered with MahaRERA as P99000078228 and the promoter has declared completion for 31 Dec 2029.
31 Dec 2029
declared completion
39months to go
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P99000078228 |
| Registered on | 29 Nov 2024 |
| Promoter-declared completion | 31 Dec 2029 |
| Current status | Certificate Signed |
| Against today | 39 months to the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Avanti Heights record 4 quarterly progress reports since registration.
4quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Filing progress reports — 4 quarterly progress reports on record since registration, with no current default.
Construction
How much construction cost has been reported?
In Avanti Heights, ₹6.93 Cr of a declared ₹13.33 Cr estimated project cost is reported as incurred, about 52.0%, as at the last certified filing with MahaRERA.
52.0%
₹6.93 Cr
of ₹13.33 Cr declared cost
Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.
Source · MahaRERA quarterly progress filing · read 12 Jul 2026
Sales
How much has actually been sold?
In Avanti Heights, 2 of 70 homes filed with MahaRERA are recorded as sold or booked, about 3%, and 68 remain available.
3%sold
2 of 70 homes
₹40.22 Lakh
committed by buyers
Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹6.46 Lakh (about 16%) is recorded as collected and ₹33.76 Lakh as receivable.
Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.
What the filings record, home by home
Read from MahaRERA on 20 September 2026
MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 9 homes carry one, and 61 of the 70 are recorded unsold. Since we started watching this ledger, 8 homes have moved out of the unsold list, most recently on 11 September 2026.
Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:
| Home | Carpet | Filed for the same home on other floors | Based on |
|---|---|---|---|
| Flat No.A/102 | 294 sqft | Rs 25.00 lakh typical, over Rs 20.00 lakh to Rs 33.51 lakh | 3 filed on this stack, floors 2–5 |
A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.
In Avanti Heights, 35 of the 61 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7 and 70 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| Avanti Heights - Residential with shopline Building | 1 | G+7 | 70 | - |
Unit mix on the filing: 67 residential and 3 non-residential (shops/offices).
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Location, Land & Connectivity
Located at Virar west, Chilpeth Road, Bolinj-Kharodi, Vasai, Palghar, 401303. Per the filed land record, the plot is bounded to the north by Chalpeth Road, to the south by Survey No 302, to the east by Grampanchayat Road and to the west by House of Shyam G Kadam. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~36 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.
| Landmark | Straight-line |
|---|---|
| Andheri MIDC / SEEPZ | 36 km |
| Powai / Hiranandani business park | 38 km |
| Chhatrapati Shivaji Int'l Airport | 40 km |
| Bandra Kurla Complex (BKC) | 43 km |
| Lower Parel / Worli business district | 50 km |
| Nariman Point / Fort | 58 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.