31 Dec 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000034907

Delivery and registration

When is the project declared for completion?

AVANTIKA CO-OP HSG SOC is registered with MahaRERA as P52000034907 and the promoter has declared completion for 31 Dec 2026.

31 Dec 2026

declared completion

3months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000034907
Registered on28 Apr 2022
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today3 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for AVANTIKA CO-OP HSG SOC record 17 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Satyaprakash Maurya is the promoter of record on 3 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

3projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for AVANTIKA CO-OP HSG SOC in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+2.

BuildingWingsFloorsDeclared completion
A1G+231 Dec 2026
B1G+231 Dec 2026

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at SUKAPUR, UGANTAK COMPLEX, Panvel, Raigarh, 410206. Per the filed land record, the plot is bounded to the north by 12, to the south by 14, to the east by 14 and to the west by 13. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Panvel

Arihant Clan Aalishan Phase I
possession by Sep 2026 · Arihant Vatika Realty Private Limited
Balaji Heritage
possession by Sep 2026 · Buildfox Realty LLP
Delta Hills
possession by Sep 2026 · Shree Ganesh Enterprises
Delta Riviera
possession by Sep 2026 · Shreenathji Organisers Pvt. Ltd.
GAJ Oasis
possession by Sep 2026 · Shiv Builders AND Developers
Green View
possession by Sep 2026 · Siddhivinayak Developers

Major developers building in Panvel

Other RERA-registered projects in Raigarh

Avas Living
possession by Dec 2027 · Avas Living Alibaug LLP
Avenue Hills
possession by Dec 2027 · Avenue Lifespaces
Avenue One
declared completion Mar 2026 · Sai Mahaavir Developers
Avenues
possession by May 2029 · Silver Homes Enterprises
Avhni
declared completion Sep 2021 · Aaum Constructions
Avighna
declared completion Mar 2023 · Rati Developers

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026