AVENTUS WESTBROOK

ANDHERI · Aventus Infrastructure LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

4units filed as unsoldInventory · 19 September 2026
31 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
23registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800048625

Delivery and registration

When is the project declared for completion?

AVENTUS WESTBROOK is registered with MahaRERA as P51800048625 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800048625
Registered on10 Jan 2023
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for AVENTUS WESTBROOK record 12 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Aventus Infrastructure Llp is the promoter of record on 2 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In AVENTUS WESTBROOK, ₹14.32 Cr of a declared ₹14.70 Cr estimated project cost is reported as incurred, about 97.4%, as at the last certified filing with MahaRERA.

97.4%

₹14.32 Cr

of ₹14.70 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In AVENTUS WESTBROOK, 19 of 23 homes filed with MahaRERA are recorded as sold or booked, about 83%, and 4 remain available.

83%sold

19 of 23 homes

₹26.09 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹22.21 Cr (about 85%) is recorded as collected and ₹3.88 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 19 registered agreements, the effective carpet rate is ₹21,055/sqft, with eight in ten falling between ₹18,949 and ₹26,555 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 101002950 sqft (88.25 sqm)₹2.00 Cr
Floor 101003950 sqft (88.25 sqm)₹2.00 Cr
Floor 101104950 sqft (88.25 sqm)₹2.00 Cr
Floor 9903950 sqft (88.25 sqm)₹2.00 Cr

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 19 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 19 homes carry one, and 4 of the 23 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
1002950 sqftRs 1.8050 cr typical, over Rs 1.7977 cr to Rs 1.8500 cr4 filed on this stack, floors 7–11

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In AVENTUS WESTBROOK, 3 of the 4 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 3 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13 and 23 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
AVENTUS WESTBROOK1G+1323-

Unit mix on the filing: 23 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at ANDHERI, NEW NAGARDAS ROAD, Mumbai City, Mumbai City, 400069. Per the filed land record, the plot is bounded to the north by CTS NO 620 AND 634, to the south by CTS NO 618, to the east by CTS 637 1 and to the west by 44 FT ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Andheri East

Anamika
possession by Sep 2026 · NEW India Constructions
Romell Myra
Deregistered by MahaRERA · possession by Sep 2026 · Romell Properties Private Limited
Romell Orbis
possession by Sep 2026 · Romell Properties Private Limited
Amey Apartments
possession by Oct 2026 · Amey Realty AND Construction LLP
Elegant Residency
possession by Dec 2026 · Elegant Builders AND Developers
Girnar Residency Wing B Phase 1
possession by Dec 2026 · Nidhaan Realty LLP

Major developers building in Andheri East

Other RERA-registered projects in Mumbai Suburban

Avenue 54
declared completion Dec 2024 · Sumer Radius Realty PVT LTD
Avenue 57
possession by Dec 2032 · V J Developer
Avenue 641
declared completion Sep 2020 · Dimple Creations
Avenue 9
possession by May 2030 · Shree Mahavir Estates Tushar Bindu
Avenue Wing B
possession by Dec 2026 · Dharmesh Constructions Private Limited
Avenue Wing B Phase 2
declared completion Dec 2025 · Dharmesh Constructions Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026