Mumbai/Project record

MahaRERA · the public record

BALI IXORA PHASE - 1

KARJAT · M/S CHANGLE REALTY

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

44units filed as unsoldInventory · 19 September 2026
30 Jun 2028declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000046575

Delivery and registration

When is the project declared for completion?

BALI IXORA PHASE - 1 is registered with MahaRERA as P52000046575 and the promoter has declared completion for 30 Jun 2028.

30 Jun 2028

declared completion

21months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000046575
Registered on19 Aug 2022
Promoter-declared completion30 Jun 2028
Current statusCertificate Signed
Against today21 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for BALI IXORA PHASE - 1 record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

How much has actually been sold?

In BALI IXORA PHASE - 1, 2 of 46 plots filed with MahaRERA are recorded as sold or booked, about 4%, and 44 remain available.

4%sold

2 of 46 plots

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for BALI IXORA PHASE - 1 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 19 September 2026

What the filings record, plot by plot

Read from MahaRERA on 19 September 2026

MahaRERA publishes, plot by plot, what this promoter filed: which plots are sold and which are not, the filed area of each, and for the sold ones the registered agreement value — the consideration filed for that specific plot. On this project 2 plots carry one, and 44 of the 46 are recorded unsold.

A filed consideration is what was registered for one plot. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the plot is available to you today. Only one observation of this ledger so far: no change can be reported yet.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2028The project is a plotting project scheduled for completion on or before June 30, 2028. It commenced on August 19, 2022, but faced delays due to financial constraints and low sales

Location, Land & Connectivity

Located at KARJAT, VILLAGE MAUJE TALUKA KARJAT, Ward GNorth, Mumbai City, 410201. Per the filed land record, the plot is bounded to the north by SURVEY NO 86, to the south by PHASE 3 AND SURVEY NO 156-3B, to the east by SURVEY NO 6 and to the west by SURVEY NO 156-2. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~58 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park58 km
Bandra Kurla Complex (BKC)60 km
Chhatrapati Shivaji Int'l Airport61 km
Andheri MIDC / SEEPZ62 km
Lower Parel / Worli business district64 km
Nariman Point / Fort64 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Karjat

Dhanlaxmi Heights
possession by Sep 2026 · Dhanlaxmi Developers
Warai Woods Ph 2
Not filing quarterly progress reports · possession by Nov 2026 · Nahar Riddhi Siddhi Developers
Jambrung Valley
possession by Nov 2026 · Kirtiraj Nanasaheb Sawant
Bliss Studio
possession by Dec 2026 · Balsam Builders
Beverly Hills
possession by Dec 2026 · Rudram Infra Projects Private Limited
Jupiter Heights
Not filing quarterly progress reports · possession by Dec 2026 · Jupiter Heights

Major developers building in Karjat

Other RERA-registered projects in Raigarh

Balibaug
declared completion Mar 2025 · Pushpam Infra LLP
Balibaug Rekreasi
possession by Dec 2026 · Pushpam Infra LLP
Balkrishna Chhabi
declared completion Jun 2024 · Balkrishna Developers
Balkrishna Nagari
declared completion Nov 2023 · Vilas Chandru Chikane
Balkrishna Paradise
declared completion Dec 2023 · Balkrishna Enterprises
Balkrishna Residency
declared completion Dec 2023 · Balkrishna Enterprises

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026