Mumbai/Project record

MahaRERA · the public record

BALKRISHNA NAGARI

NEAR GOVT HOSPITAL · VILAS CHANDRU CHIKANE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

15 Nov 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

15 Nov 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000018664

Delivery and registration

When is the project declared for completion?

BALKRISHNA NAGARI is registered with MahaRERA as P52000018664 and the promoter has declared completion for 15 Nov 2023.

15 Nov 2023

declared completion

34months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000018664
Registered on22 Nov 2018
Promoter-declared completion15 Nov 2023
Current statusCertificate Signed
Against todayabout 34 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for BALKRISHNA NAGARI record 21 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 21 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for BALKRISHNA NAGARI in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
WING A,B,C,D,E,F1G+315 Nov 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at NEAR GOVT HOSPITAL, ADJACENT TO MUMBAI GOA HIGHWAY, Poladpur, Raigarh, 402303. Per the filed land record, the plot is bounded to the north by RAJU DHUMAL PLOT, to the south by N G KADAM PLOT, to the east by VILAS CHIKANE PLOT and to the west by NAGESH PAWAR PLOT. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Poladpur

Ramchandra Nana Appartment
possession by Dec 2027 · Sanjay Nana Jadhav
Swaraj Complex
possession by Mar 2028 · AMI Realty Developers LLP
Shiv Plaza
possession by Dec 2028 · Gaikwad Builders AND Developers
Siddhi Samruddhi Residency
possession by Dec 2028 · Surendra Kashiram Chavan
Mangalmurti Park
declared completion Jul 2026 · Elanza Developer
Shree Samarth Krupa A/B Wing
Not filing quarterly progress reports · declared completion Jun 2025 · Rajesh Shantaram Mahadik

Other RERA-registered projects in Raigarh

Balkrishna Paradise
declared completion Dec 2023 · Balkrishna Enterprises
Balkrishna Residency
declared completion Dec 2023 · Balkrishna Enterprises
Bandal VED Bhumi-Phase 2
declared completion Apr 2025 · Not Available
Bandivadekar Residency
declared completion Dec 2022 · Mangesh Bhalchandra Mhatre
Bankers Tower CO OP HSG SO
declared completion Dec 2017 · Bankers Tower CHS
Bansidhar
possession by Dec 2026 · Kamal Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026