MahaRERA · the public record
MANGALMURTI PARK
Poladpur · ELANZA DEVELOPER
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
31 Jul 2026
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P52000010385
Delivery and registration
When is the project declared for completion?
MANGALMURTI PARK is registered with MahaRERA as P52000010385 and the promoter has declared completion for 31 Jul 2026.
31 Jul 2026
declared completion
2months past
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P52000010385 |
| Registered on | 24 Aug 2017 |
| Promoter-declared completion | 31 Jul 2026 |
| Current status | Certificate Signed |
| Against today | about 2 months past the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for MANGALMURTI PARK record 36 quarterly progress reports since registration.
36quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Filing progress reports — 36 quarterly progress reports on record since registration, with no current default.
Construction
How much construction cost has been reported?
In MANGALMURTI PARK, ₹29.89 Cr of a declared ₹29.89 Cr estimated project cost is reported as incurred, about 100.0%, as at the last certified filing with MahaRERA.
100.0%
₹29.89 Cr
of ₹29.89 Cr declared cost
Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.
Source · MahaRERA quarterly progress filing · read 12 Jul 2026
Sales
How much has actually been sold?
In MANGALMURTI PARK, 212 of 269 homes filed with MahaRERA are recorded as sold or booked, about 79%, and 57 remain available.
79%sold
212 of 269 homes
₹37.08 Cr
committed by buyers
Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹36.77 Cr (about 99%) is recorded as collected and ₹30.79 Lakh as receivable. The project registers 277 homes in total, while this sold/unsold inventory filing covers 269 of them.
Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026
What buyers actually paid: across 212 registered agreements, the effective carpet rate is ₹3,397/sqft, with eight in ten falling between ₹2,807 and ₹5,932 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.
The inventory filing also declares: 8 not for sale.
What the filings record, home by home
Read from MahaRERA on 16 September 2026
MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 212 homes carry one, and 57 of the 277 are recorded unsold.
Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:
| Home | Carpet | Filed for the same home on other floors | Based on |
|---|---|---|---|
| 308 | 617 sqft | Rs 21.12 lakh typical, over Rs 16.00 lakh to Rs 23.50 lakh | 6 filed on this stack, floors 1–7 |
A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.
In MANGALMURTI PARK, 34 of the 57 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7 and 277 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| A-WING | 1 | G+4 | 116 | 30 Dec 2022 |
| B-WING | 1 | G+7 | 63 | 30 Dec 2022 |
| C-WING | 1 | G+7 | 98 | 30 Dec 2022 |
| D-WING | 1 | G+4 | - | - |
Unit mix on the filing: 199 residential and 78 non-residential (shops/offices).
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Deadline Extensions
The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.
| From | Extended to | Stated reason |
|---|---|---|
| as registered | 30 Dec 2022 | Due to current covide-19 pandemic we are unable to complete project in time. |
| 30 Dec 2022 | 30 Dec 2023 | Due to Covide-19 and frequent flood condition in rainy season in the area of mahad and poladpur. |
| 30 Dec 2023 | 31 Jul 2026 | The project faced delays due to factors beyond the promoter’s control. Owing to its outside location, no sale of units was achieved during the initial period, resulting in financia |
Location, Land & Connectivity
Located at Poladpur, Nr.Government Hospital, Poladpur, Raigarh, 402303. Per the filed land record, the plot is bounded to the north by LAGU SURVEY NO 56 and 57, to the south by HISSA NO 55-2 and LAGU SURVEY NO 54, to the east by 60 MTR WIDE ROAD and to the west by LAGU SURVEY NO 52 and 57. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~131 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.
| Landmark | Straight-line |
|---|---|
| Nariman Point / Fort | 124 km |
| Lower Parel / Worli business district | 131 km |
| Bandra Kurla Complex (BKC) | 135 km |
| Chhatrapati Shivaji Int'l Airport | 138 km |
| Powai / Hiranandani business park | 139 km |
| Andheri MIDC / SEEPZ | 142 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.