Mumbai/Project record

MahaRERA · the public record

Bhagirathi C Wing

Wada · Chittaranjan Estates Pvt. Ltd.

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000010523

Delivery and registration

When is the project declared for completion?

Bhagirathi C Wing is registered with MahaRERA as P99000010523 and the promoter has declared completion for 31 Dec 2024.

31 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000010523
Registered on31 Aug 2017
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Bhagirathi C Wing record 30 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 30 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Chittaranjan Estates is the promoter of record on 3 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

3projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Bhagirathi C Wing in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
Bhagirathi C Wing1G+330 Aug 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 4 times, as recorded on the register.

FromExtended toStated reason
as registered31 Oct 2020Due to revision in FSI rules, we had revised our plan to G + 3. And we had submitted revised plan copy to authority on 04th December 2017. But the approval for same is still awaiti
31 Oct 202031 Aug 2023delay of approval from the competent authority for sanction of plans
31 Aug 202330 Mar 2024There were changes in th eplan which had to get approved from the town planning and also due to labour issues.
30 Mar 202431 Dec 2024Delay due to unavailability of materials on time and labour issues. Financial issues.

Location, Land & Connectivity

Located at Wada, Shivaji Nagar, Kurla, Mumbai Suburban, 421312. Per the filed land record, the plot is bounded to the north by Bhagirathi A wing and open land, to the south by Internal 9 meter road, to the east by Open Land and to the west by Bhagirathi Wing B. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~62 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park62 km
Andheri MIDC / SEEPZ63 km
Chhatrapati Shivaji Int'l Airport67 km
Bandra Kurla Complex (BKC)69 km
Lower Parel / Worli business district78 km
Nariman Point / Fort85 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Wada

SAI Kala Complex
Not filing quarterly progress reports · possession by Dec 2026 · Swastik Properties
Dream Park
possession by Jan 2028 · Dream Builders
Dream Park
possession by Dec 2030 · Dream Builders
Gandhi Industrial Park
Deregistered by MahaRERA · declared completion Jan 2026 · Gandhi Builders PVT LTD

Other RERA-registered projects in Palghar

Bhagwati AND Jeevan Heights
declared completion Dec 2024 · Shree Ganesh Builders & Developers
Bhagwati Vastu C Wing
possession by Dec 2030 · Bhargavi Builders And Developers
Bhagwati Vastu D Wing
possession by Jun 2029 · Shagun Builders AND Developers
Bhairav Complex Bldg NO 1
declared completion Dec 2024 · Bhairav Enterprises
Bhakti Apartment, Building No.6, Wing A
declared completion Jun 2023 · M/S Saryu Builders & Developers
Bhakti Apartment Phase II
possession by Dec 2026 · Saryu Builders & Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026