Mumbai/Project record

MahaRERA · the public record

GANDHI INDUSTRIAL PARK

Mumbai Suburban · GANDHI BUILDERS PVT LTD

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jan 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jan 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000005517

Delivery and registration

When is the project declared for completion?

GANDHI INDUSTRIAL PARK is registered with MahaRERA as P99000005517 and the promoter has declared completion for 30 Jan 2026.

30 Jan 2026

declared completion

8months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000005517
Registered on11 Aug 2017
Promoter-declared completion30 Jan 2026
Current statusCertificate Signed
Against todayabout 8 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for GANDHI INDUSTRIAL PARK record 35 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Deregistered — MahaRERA has deregistered this project — it is off the register.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Gandhi Builders is the promoter of record on 45 projects registered with MahaRERA, 9 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

45projects

registered with MahaRERA

9flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for GANDHI INDUSTRIAL PARK in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date.

BuildingWingsFloorsDeclared completion
GANDHI INDUSTRIAL PARK1-31 Oct 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Andheri, Mumbai Suburban, 421312. Per the filed land record, the plot is bounded to the north by PLOT 284 285, to the south by PLOT No 296 297 316, to the east by PLOT 321 and to the west by palsai road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~65 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park65 km
Andheri MIDC / SEEPZ65 km
Chhatrapati Shivaji Int'l Airport69 km
Bandra Kurla Complex (BKC)72 km
Lower Parel / Worli business district80 km
Nariman Point / Fort88 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Wada

SAI Kala Complex
Not filing quarterly progress reports · possession by Dec 2026 · Swastik Properties
Dream Park
possession by Jan 2028 · Dream Builders
Dream Park
possession by Dec 2030 · Dream Builders
Bhagirathi C Wing
declared completion Dec 2024 · Chittaranjan Estates Pvt. Ltd.

Other RERA-registered projects in Palghar

Ganesh Apartment
declared completion Mar 2024 · Tarkeshwar Hariprasad RAI
Ganesh Apartment
declared completion Jan 2022 · Vishnu Govind Patil
Ganesh Darshan Building -1 Type -A
possession by Dec 2028 · Dwarkesh Developers
Ganga CO OP HSG LTD
declared completion May 2026 · Viva Rium Builders & Developers
Gangotri Heights
possession by Dec 2028 · Shree Yogi Builders & Developer
Gangotri Sadan
declared completion Aug 2025 · Devikripa Developers

What to verify (inactive registration)

  1. Download the MahaRERA order stating the reason for deregistration or suspension — this is public on the portal.
  2. Check whether the developer has filed a challenge in the Appellate Tribunal and whether the order is stayed.
  3. Do not make any further payments until the registration status is restored or you obtain legal advice.
  4. Contact MahaRERA's helpdesk for guidance on alternative arrangements or pending dues.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026