Mumbai/Project record

MahaRERA · the public record

BHAGWATI VILA WING B

BHAJI MARKET · SHANTINATH ENTERPRISES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

29 Jun 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

29 Jun 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700008738

Delivery and registration

When is the project declared for completion?

BHAGWATI VILA WING B is registered with MahaRERA as P51700008738 and the promoter has declared completion for 29 Jun 2022.

29 Jun 2022

declared completion

51months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700008738
Registered on19 Aug 2017
Promoter-declared completion29 Jun 2022
Current statusCertificate Signed
Against todayabout 51 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for BHAGWATI VILA WING B record 20 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 20 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Shantinath Enterprises is the promoter of record on 3 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

3projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for BHAGWATI VILA WING B in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.

BuildingWingsFloorsDeclared completion
Bhagwati Vila Wing B1G+1229 Jun 2020

Legal and disputes

What disputes are disclosed?

15 complaints are on the MahaRERA record for BHAGWATI VILA WING B, with orders passed in 15 of them.

15complaints

15with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019260913/02/2020Mrs. Girija Nandkumar Inamdar vs Shantinath Enterprisesorder passed
CC00600000039779513/10/2023SANKET BHARAT SHAH vs M/S. SHANTINATH ENTERPRISESorder passed
CC00600000039780316/10/2023Jyoti pravin Doshi vs Shantinath Enterprisesorder passed
CC00600000039780416/10/2023Jyoti pravin Doshi vs M/s. Shantinath Enterprisesorder passed
CC00600000039780513/10/2023Bipin V Shah HUF vs SHANTINATH ENTERPRISESorder passed
CC00600000039780613/10/2023Bipin V Shah HUF vs SHANTINATH ENTERPRISESorder passed
CC00600000039780816/10/2023Rajvi Rahul Shah vs SHANTINATH ENTERPRISESorder passed
CC00600000039780913/10/2023BHADRA BIPIN SHAH vs SHANTINATH ENTERPRISESorder passed
CC00600000039781013/10/2023BHADRA BIPIN SHAH vs SHANTINATH ENTERPRISESorder passed
CC00600000039781116/10/2023PRAVIN C DOSHI vs SHANTINATH ENTERPRISESorder passed
CC00600000039781216/10/2023PRAVIN C DOSHI vs SHANTINATH ENTERPRISESorder passed
CC00600000039781413/10/2023Virti Bipin Shah vs SHANTINATH ENTERPRISESorder passed
CC00600000039781513/10/2023Virti Bipin Shah vs SHANTINATH ENTERPRISESorder passed
CC00600000039781713/10/2023RAHUL B SHAH HUF vs SHANTINATH ENTERPRISESorder passed
CC00600000041868414/01/2024SHREYAS SUDHIR JOSHI vs M/S. SHANTINATH ENTERPRISESorder passed

Legal & Litigation

The promoter has declared 5 court cases on this project to MahaRERA. 5 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
KalyanRCS 572/162016Pending
Kalyan573/162016Pending
Kalyan78/172017Pending
Kalyan54/172017Pending
Kalyan574/162016Pending

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered29 Jun 2020Our Managing partner, Mr. Ashok Bhanji Joshi, who was handling the case expired on 01.01.2018. In his absence it became difficult for other partners to handle project financially a
29 Jun 202029 Dec 2021That at the time of applying for RERA registration we envisaged to complete the project on or before 30/06/2019.However one of our partnerMr. Ashok Bhanji Joshi who was co-ordinati

Location, Land & Connectivity

Located at BHAJI MARKET, NEHRU ROAD, Kalyan, Thane, 421201. Per the filed land record, the plot is bounded to the north by SAI DARSHAN BUILDING, to the south by 15MTR WIDE DP ROAD, to the east by 15MTR WIDE DP ROAD and to the west by 15MTR WIDE DP ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~22 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park22 km
Andheri MIDC / SEEPZ25 km
Chhatrapati Shivaji Int'l Airport27 km
Bandra Kurla Complex (BKC)28 km
Lower Parel / Worli business district36 km
Nariman Point / Fort42 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shantinath Enterprises is the promoter on 3 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Shantinath Enterprises

Shantinath Enterprises
FlaggedPalghar
Shantinath Enterprises
FlaggedPalghar

Other RERA-registered projects in Dombivli East

Mahalaxmi Ashish D Wing
possession by Sep 2026 · Swastik Enterprises
NAV Pratima CO. OP. Hsg. Soc. LTD
possession by Sep 2026 · Narendra Kalyanji Patel
Sumati Skyline
possession by Sep 2026 · Subhash Skyline Infra
Vinayak Prerana
possession by Sep 2026 · Nakshatra Group
Shanu Majestic
possession by Dec 2026 · Fortune Group Of Construction
Balaji Annex
possession by Dec 2026 · M/S OM Swayambhu Siddhivinayak Builders

Major developers building in Dombivli East

Other RERA-registered projects in Thane

Bhairaav Milestone Phase II
possession by Dec 2026 · Sharpmind Consultancy Services Private L
Bhairav Enclave
declared completion Aug 2026 · Leena Estate Venture
Bhakti Enclave
declared completion Jul 2019 · Mangalmurti Enterprises
Bhakti Park
declared completion Dec 2022 · Milan Jayantilal Salot
Bhakti Plaza
declared completion Sep 2022 · Laxmi Construction
Bhakti Vighnesh
declared completion Dec 2021 · Vineet Dattatray Thanekar

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026