MahaRERA Property Intelligence · Mumbai Suburban

BHAGYAYOG CHSL

P51800010227 · promoter Navkar Builder And

Certificate SignedDue 31 Dec 2018

Delivery & Registration

MahaRERA registrationP51800010227
Registered on24 Aug 2017
Promoter-declared completion31 Dec 2018
Current statusCertificate Signed
Against todayabout 91 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Navkar Builder And is the promoter of record on 87 projects, of which 11 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
BHAGYAYOG CHSL1G+13-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay City Civil Court8052016Proceeding Is Going On

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 400092. Per the filed land record, the plot is bounded to the north by 18 METER WIDE SHIMPOLI ROAD, to the south by SUB PLOT NO 29 OF FINAL PLOT 624 - BRIJ APARTMENT, to the east by SUB PLOT NO 13 OF FINAL PLOT 624 - VEG TREAT HOTEL and to the west by SUB PLOT NO 13 OF FINAL PLOT 624 - NEEL KAMAL APT. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ11 km
Powai / Hiranandani business park13 km
Chhatrapati Shivaji Int'l Airport15 km
Bandra Kurla Complex (BKC)18 km
Lower Parel / Worli business district25 km
Nariman Point / Fort33 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Navkar Builder AND Developers is the promoter on 2 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Navkar Builder AND Developers

Navkar Builder AND Developers
Past its declared completion dateMumbai Suburban

Other RERA-registered projects in Borivali West

Rishabraj Aradhana
possession by Jul 2026 · H Rishabraj Realty
SBI Ragvihar CHS
possession by Jul 2026 · Tuvin Consultancy LLP
Avyukta Neelkamal
possession by Sep 2026 · Shivoham Associates
Gopal Terrace Co-Operative Housing Society LTD
possession by Sep 2026 · Polo Infra Developers Private Limited
House Of Shreeji Sharan
possession by Sep 2026 · Miles Infra LLP
Sai Signature Spaces
possession by Sep 2026 · Ramachandran Munisawmy Narayan

Major developers building in Borivali West

Other RERA-registered projects in Mumbai Suburban

Bhakti Pride
possession by Dec 2027 · Bhakti Homes
Bhalla Chsl Jupiter - Venus
possession by Dec 2026 · Chetna Global
Bhandup Amol CHS LTD
possession by Dec 2026 · Sudhanshu Infrastructures Private Limite
Bhandup Citizen CHS Ltd
possession by Mar 2028 · Castle Floors PMS Pvt Ltd
Bhandup Sanmitra CHS LTD
declared completion Jun 2024 · Shraddha Landmark Private Limited
Bhandup Siddhivinayak CHS Ltd
possession by Jun 2028 · Shraddha Landmark Private Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026