MahaRERA Property Intelligence · Mumbai Suburban

Bhandup Citizen CHS Ltd

P51800015109 · Bhandup W · promoter Castle Floors Pms

Certificate SignedDue 31 Mar 2028

Delivery & Registration

MahaRERA registrationP51800015109
Registered on31 Jan 2018
Promoter-declared completion31 Mar 2028
Current statusCertificate Signed
Against today20 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Castle Floors Pms is the promoter of record on 16 projects, of which 3 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~38.5% of the estimated project cost incurred as of the last certificate (₹10.00 Cr spent against a ₹26.00 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 38 homes filed with MahaRERA, 0 are sold/booked and 38 remain available (~0% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. Note: the project registers 78 homes in total, but this sold/unsold inventory filing covers only 38 of them — the other 40 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 121201545 sqft (50.65 sqm)₹80
Floor 121202545 sqft (50.65 sqm)₹80
Floor 121203545 sqft (50.65 sqm)₹80
Floor 121204545 sqft (50.65 sqm)₹80
Floor 131301545 sqft (50.65 sqm)₹80
Floor 131302545 sqft (50.65 sqm)₹80
Floor 131303545 sqft (50.65 sqm)₹80
Floor 131304545 sqft (50.65 sqm)₹80
Floor 141401545 sqft (50.65 sqm)₹80
Floor 141402545 sqft (50.65 sqm)₹80
Floor 141403545 sqft (50.65 sqm)₹80
Floor 141404545 sqft (50.65 sqm)₹80
Floor 151501545 sqft (50.65 sqm)₹80
Floor 151502545 sqft (50.65 sqm)₹80
Floor 151503545 sqft (50.65 sqm)₹80
Floor 161601545 sqft (50.65 sqm)₹80
Floor 161602545 sqft (50.65 sqm)₹80
Floor 161603545 sqft (50.65 sqm)₹80
Floor 161604545 sqft (50.65 sqm)₹80
Floor 171701545 sqft (50.65 sqm)₹80
Floor 171702545 sqft (50.65 sqm)₹80
Floor 171703545 sqft (50.65 sqm)₹80
Floor 171704545 sqft (50.65 sqm)₹80
Floor 181801545 sqft (50.65 sqm)₹80
Floor 181802545 sqft (50.65 sqm)₹80
Floor 181803545 sqft (50.65 sqm)₹80
Floor 181804545 sqft (50.65 sqm)₹80
Floor 191901545 sqft (50.65 sqm)₹80
Floor 191902545 sqft (50.65 sqm)₹80
Floor 191903545 sqft (50.65 sqm)₹80
Floor 191904545 sqft (50.65 sqm)₹80
Floor 202001545 sqft (50.65 sqm)₹80
Floor 202002545 sqft (50.65 sqm)₹80
Floor 202003545 sqft (50.65 sqm)₹80
Floor 202004545 sqft (50.65 sqm)₹80
Floor 212101545 sqft (50.65 sqm)₹80
Floor 212102545 sqft (50.65 sqm)₹80
Floor 8801545 sqft (50.65 sqm)₹80

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7 and 78 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Bhandup Citizen CHS Ltd1G+77831 Dec 2020

Unit mix on the filing: 78 residential.

Complaints & Orders

3 complaints are on the MahaRERA record for this project, with orders passed in 3. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000019625908/03/2021Bhandup Citizen Co-operative Housing Society Limited (society) vs Mr. Chetan Patil - Castle floor project management service pvt. ltd.order passed
CC00600000020949722/12/2021Bhandup Citizens CHS Ltd (society) vs Castle Floor Project management Services Pvt Ltdorder passed
CC00600000039580715/05/2023BHANDUP CITIZEN CHSL (society) vs CASTLE FLOOR PROJECT MANGEMENT SERVICE PVT LTDorder passed

A co-operative housing society is the complainant here (Bhandup Citizen Co-operative Housing Society Limited) and MahaRERA has already passed an order. On a redevelopment, that is the LANDOWNER society in dispute with its developer — a different order of risk from a single buyer's grievance, because it can touch the development rights, the society's consent, and ultimately the title to your flat. Have your lawyer read this order and the development agreement together before you commit.

Legal & Litigation

The promoter has declared 4 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Before The Sole Arbitrator Mr Minoo Siodia1442016Ongoing
High Court4632017Ongoing
City Civil6432021Closed
High Court1282023Closed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Jun 202131 May 2023Dear Sir, we require extension for completion deadline of the project due to covid related effects of slowing down site activity and due to a litigation in city civil court bearing
30 Jun 202131 Mar 2028The project was delayed due to issues with the society and it went in to litigation . Finally in August 2026 we filed consent terms in city civil court and now we shall be able to

Location, Land & Connectivity

Located at Bhandup W, Village Road, Khandelwal Marg, Kurla, Mumbai Suburban, 400078. Per the filed land record, the plot is bounded to the north by Mangal Manisha CHS Ltd, to the south by Road, to the east by Road and to the west by GKW Sankey CHS Ltd. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)2 km
Chhatrapati Shivaji Int'l Airport4 km
Powai / Hiranandani business park7 km
Andheri MIDC / SEEPZ8 km
Lower Parel / Worli business district9 km
Nariman Point / Fort16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhandup West

Shraddha Evoque
possession by Aug 2026 · Shraddha Landmark Private Limited
Primo
possession by Sep 2026 · Ceear Land Developers LLP
Aureate
possession by Dec 2026 · Beauty Ganraj Construction LLP
Fairmont
possession by Dec 2026 · Trident Ozone LLP
Neptune Eleve Wing A
Developer in insolvency (NCLT) · possession by Dec 2026 · Neptune Ventures AND Developers Private
Neptune Eleve Wing B
Developer in insolvency (NCLT) · possession by Dec 2026 · Neptune Ventures AND Developers Private

Major developers building in Bhandup West

Other RERA-registered projects in Mumbai Suburban

Bhandup Sanmitra CHS LTD
declared completion Jun 2024 · Shraddha Landmark Private Limited
Bhandup Siddhivinayak CHS Ltd
possession by Jun 2028 · Shraddha Landmark Private Limited
Bhandup Vijaysadhana CHS
declared completion Mar 2018 · Karan Developers
Bhanu Jyoti Chsl
declared completion Dec 2024 · Namo Realty Ventures LLP
Bhanushali Nagar
declared completion Jun 2026 · Shree Kutchhi Bhanushali Seva Samaj Trus
Bharat Auravistas
possession by Jul 2029 · Bharat Realty Venture Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026