MahaRERA Property Intelligence · Mumbai Suburban
P51800001724 · Near Shangrilla Biscuit Factory · promoter Ceear Land Developers
| MahaRERA registration | P51800001724 |
| Registered on | 29 Jul 2017 |
| Promoter-declared completion | 30 Sep 2026 |
| Current status | Certificate Signed |
| Against today | 2 months to the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+23.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| Primo | 1 | G+23 | 31 Dec 2020 |
38 complaints are on the MahaRERA record for this project, with orders passed in 37. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC006000000209909 | 22/02/2022 | KRUPESH PRAMOD THAKKAR/ KOMAL KRUPESH THAKKAR vs CEEAR LAND DEVELOPERS LLLP | order passed |
| CC006000000210091 | 18/02/2022 | Abhishek Walavalkar vs CEEAR LAND DEVELOPERS LLP | order passed |
| CC006000000210082 | 18/02/2022 | Amey Ram Walavalkar vs CEEAR LAND DEVELOPERS LLP | order passed |
| CC006000000210088 | 18/02/2022 | DEEPAK POTADAR vs CEEAR LAND DEVELOPERS LLP | order passed |
| CC006000000210094 | 18/02/2022 | Vivek Kalambe vs CEEAR LAND DEVELOPERS LLP | order passed |
| CC006000000210092 | 18/02/2022 | Ravindra Pawar vs CEEAR LAND DEVELOPERS LLP | order passed |
| CC006000000210518 | 24/03/2022 | Minakshi Pappu Yadav vs Ceear Land developers LLP | order passed |
| CC006000000220870 | 18/04/2022 | SHIVSHANKAR SAHU vs CEEAR LAND DEVELOPERS LLP | order passed |
| CC006000000220883 | 19/04/2022 | MAHESHKKUMAR G SAHU vs CEAAR LAND DEVELOPERS LLP | order passed |
| CC006000000220884 | 19/04/2022 | MAHESHKKUMAR G SAHU vs CEAAR LAND DEVELOPERS LLP | order passed |
| CC006000000220889 | 20/04/2022 | GIRISH G GUPTA vs CEAAR LAND DEVELOPERS LLP | order passed |
| CC006000000220893 | 20/04/2022 | KALPESH G KAMBLE vs CEAAR LAND DEVELOPERS LLP | order passed |
| CC006000000220901 | 21/04/2022 | NIKHIL V KANADE vs CEAAR LAND DEVELOPERS LLP | order passed |
| CC006000000220902 | 21/04/2022 | JAYESH KAILASH POTWADE vs CEAAR LAND DEVELOPERS LLP | order passed |
| CC006000000220910 | 21/04/2022 | MRS LAVANYA LAXMAN DHURI vs CEAAR LAND DEVELOPERS LLP | order passed |
| CC006000000231153 | 12/05/2022 | MANUBHAI PANCHAL vs CEAAR LAND DEVELOPERS LLP | order passed |
| CC006000000231266 | 23/05/2022 | VINAY SITARAM GUPTA vs CEAAR LAND DEVELOPERS LLP | order passed |
| CC006000000231268 | 23/05/2022 | VIKAS SITARAM GUPTA vs CEAAR LAND DEVELOPERS LLP | order passed |
| CC006000000231294 | 25/05/2022 | JITENDRA GUPTA vs CEAAR LAND DEVELOPERS LLP | order passed |
| CC006000000261957 | 18/07/2022 | Merwyn Pawar vs Ceeat Land Developers LLP | order passed |
| CC006000000292319 | 25/08/2022 | Umeshchand Shyambihari Pandey vs M/s. Ceear Land Developers LLP | order passed |
| CC006000000303489 | 29/11/2022 | SAMEER A SHAIKH vs CEEAR LAND DEVELOPERS | order passed |
| CC006000000344237 | 14/02/2023 | Prasad Chandrakant Khadpe vs CEEAR LAND DEVELOPERS LLP | order passed |
| CC006000000344271 | 10/02/2023 | RAJAN ASWANI vs CEEAR LAND DEVELOPERS LLP | order passed |
| CC006000000354364 | 15/02/2023 | Nitin Shetty vs Ceear Land Developers LLP | order passed |
| CC006000000354366 | 15/02/2023 | SURESH BABURAV AMBOKAR vs CEEAR LAND DEVELOPERS LLP | order passed |
| CC006000000396384 | 22/06/2023 | RAJU GUPTA vs CEAAR LAND DEVELOPERS | order passed |
| CC006000000396594 | 11/07/2023 | MR DAYANAND TUKARAM KADAM vs CEEAR LAND DEVELOPERS LLP | order passed |
| CC006000000396825 | 02/08/2023 | Subhan Allah Ikramullah Khan vs Ceear Land Developers LLP | order passed |
| CC006000000428939 | 24/01/2024 | Vaibhav Pradeep Palav vs Ceear Land Developers | order passed |
| CC006000000429036 | 01/02/2024 | Shankar Nagesh Kadu vs CEEAR Land Developers | order passed |
| CC006000000429097 | 04/02/2024 | Sadanand Ganpat Satam vs Ceear Land Developers LLP | order passed |
| CC006000000429099 | 04/02/2024 | Alekh Gupta vs Ceear Land Developer LLP | order passed |
| CC006000000429101 | 04/02/2024 | Sachin Shridhar Dhumal vs Ceear Land Developers LLP | order passed |
| CC006000000429425 | 06/03/2024 | PRIMO ALLOTTEES ASSOCIATION vs Ceear Land Developers LLP | order passed |
| CC12400091 | 13/09/2024 | Vivek Basant Kumar Porwal vs Ceear Land Developers LLP | order passed |
| CC12503782 | 29/10/2025 | Sheeba David Nadar vs Ceear Land Developers LLP | order passed |
| CC12604072 | 30/06/2026 | Biju Francis Koola vs Ceear Land Developers LLP | pending / no order on file |
The promoter has had the MahaRERA completion deadline formally extended 3 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 31 Mar 2024 | 30 Jun 2022 | The Promoter was totally in control of the project timelines at the time when initial approvals were obtained until the time the DCPR 2034 was decided to be sanctioned. Lot of time |
| 31 Mar 2024 | 31 Mar 2024 | The RERA certificate of the project has expired on 31.12.2022 and all sales and financial inflows to the project have stopped. Which has reduced the ongoing construction activities |
| 30 Jun 2021 | 30 Sep 2026 | 1. The Applicant further states that the Applicant couldn’t obtain requisite consent of 51% in spite of all the efforts. The RCC structure is complete till 17th Residential floor/f |
Located at Near Shangrilla Biscuit Factory , Off. LBS Road, Mumbai City, Mumbai City, 400078. Per the filed land record, the plot is bounded to the north by S No 201, to the south by G D Marg, to the east by Plot B and to the west by S No 201. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Powai / Hiranandani business park | 6 km |
| Andheri MIDC / SEEPZ | 8 km |
| Chhatrapati Shivaji Int'l Airport | 11 km |
| Bandra Kurla Complex (BKC) | 12 km |
| Lower Parel / Worli business district | 21 km |
| Nariman Point / Fort | 28 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in Primo?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026