MahaRERA Property Intelligence · Mumbai Suburban

Bhanu Jyoti CHSL

P51800046215 · Malad East · promoter Namo Realty Ventures

Certificate SignedDue 31 Dec 2024

Delivery & Registration

MahaRERA registrationP51800046215
Registered on20 Jun 2022
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 19 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Namo Realty Ventures is the promoter of record on 24 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
East Avenue - A Wing1G+11-
East Avenue - B Wing1G+10-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Malad East, Nivetia Road, Borivali, Mumbai Suburban, 400097. Per the filed land record, the plot is bounded to the north by CTS No -554, to the south by CTS No -557, to the east by 13 Mtr Wide Nivetiya Nagar Road and to the west by Railway Track. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Malad East

DEM Phoenix
possession by Jul 2026 · DEM Buildwell
Rajhans Solitaire
possession by Aug 2026 · Rajhans Residency
Amann Highland Park
possession by Oct 2026 · MS Relliance Construction CO
Gami And Jaydeep Ventura Commercial Hub
possession by Oct 2026 · M/S Real Infrastructure CO
Parmar Pearl - JAY Koteshwar Nagar CHS LTD
possession by Nov 2026 · Parmar Constructions Private Limited
Neelyog Virat -A Wing
possession by Dec 2026 · Neelyog Construction Pvt Ltd

Other RERA-registered projects in Mumbai Suburban

Bhanushali Nagar
declared completion Jun 2026 · Shree Kutchhi Bhanushali Seva Samaj Trus
Bharat Auravistas
possession by Jul 2029 · Bharat Realty Venture Private Limited
Bharti Aarambh
declared completion Mar 2026 · Bharti Constructions
Bharti Villa
possession by Dec 2027 · Jain Associates
Bhavani Plaza
declared completion Jun 2026 · Padmakar Purushottam Gokarna
Bhavesha CO-Operative Housing Society LTD
declared completion Nov 2023 · Beautiful Properties Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026