MahaRERA Property Intelligence · Mumbai Suburban
P51800002369 · BORIVALI EAST · promoter Trumph Developers
| MahaRERA registration | P51800002369 |
| Registered on | 31 Jul 2017 |
| Promoter-declared completion | 31 Dec 2026 |
| Current status | Certificate Signed |
| Against today | 5 months to the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
MahaRERA's cost filing puts construction at ~98.7% of the estimated project cost incurred as of the last certificate (₹28.66 Cr spent against a ₹29.03 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.
Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.
Of 76 homes filed with MahaRERA, 75 are sold/booked and 1 remain available (~99% sold) — nearly sold out — little inventory left, so you're buying into an established buyer base. Buyers have committed ₹50.21 Cr in agreement value so far. Of that, ₹47.92 Cr (~95%) is already collected, ₹2.29 Cr receivable — a read on how far along these sales really are. Note: the project registers 136 homes in total, but this sold/unsold inventory filing covers only 76 of them — the other 60 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.
What buyers actually paid: across 75 registered agreements, the effective carpet rate is ₹12,877/sqft (typical range ₹10,196–₹16,197) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.
The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:
| Floor | Unit | Carpet | Reckoner value |
|---|---|---|---|
| Floor 17 | B 1704 | 582 sqft (54.11 sqm) | ₹69.84 Lakh |
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+20 and 136 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| Wing A | 1 | G+20 | 60 | - |
| Wing B | 1 | G+20 | 76 | - |
Unit mix on the filing: 136 residential.
11 complaints are on the MahaRERA record for this project, with orders passed in 11. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC006000000195404 | 26/12/2020 | Vinod Somaru Prajapati vs Trumph Developers | order passed |
| CC006000000195500 | 03/01/2021 | Sharad Gulabrao Pawar vs Trumph Developers | order passed |
| CC006000000195577 | 10/01/2021 | SHAISHAV SHAH vs TRUMPH DEVELOPER | order passed |
| CC006000000195579 | 10/01/2021 | AKANKSHA ANIL LAD vs TRUMPH DEVELOPERS | order passed |
| CC006000000195580 | 10/01/2021 | SHOBHA ANIL TULASKAR vs Trumph Developers | order passed |
| CC006000000195581 | 10/01/2021 | PRASAD PANDURANG PEDNEKAR vs TRUMPH DEVELOPER | order passed |
| CC006000000195584 | 10/01/2021 | SADANANAD SHIVRAM SURVE vs TRUMPH DEVELOPER | order passed |
| CC006000000195585 | 12/01/2021 | Shyamnrayan Dhanjooram Prajapati vs TRUMPH DEVELOPER | order passed |
| CC006000000195582 | 10/01/2021 | TEJPALSINGH SETHI vs TRUMPH DEVELOPER | order passed |
| CC006000000195583 | 10/01/2021 | SHRIKANT BHIKAJI KELKAR vs Trumph Developers | order passed |
| CC006000000210437 | 19/03/2022 | SAMPADA SURVE AND SURESH SURVE vs TRUMPH DEVELOPERS | order passed |
The promoter has had the MahaRERA completion deadline formally extended 5 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 30 Jun 2024 | 30 Dec 2020 | APPLIED FOR FURTHER C.C. FROM MHADA BUT DEMAND LETTER IS NOT YET RECEIVED. |
| 30 Jun 2024 | 31 Dec 2022 | DUE TO COVID WORK AT SITE WAS NOT CARRIED OVER. PLEASE GRANT EXTENSION U/S 7(3). POSSESION TO ONE BUILDING CONSISTING OF ORIGINAL TENENTS HAVE BEEN GIVE. |
| 30 Jun 2024 | 30 Jun 2024 | DELAY DUE TO PENDING APRROVAL. Commencement Certificate for 14-20th is under process. Total apartment includes 60 apartment allotted to existing tenant under SRA Scheme. Out of b |
| 31 Dec 2019 | 30 Sep 2025 | In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various r |
| 31 Dec 2019 | 31 Dec 2026 | Dear Sir/Ma’am, We, Trumph Developers, hereby declare the following with respect to the project “BLDG NO.1 DAHISAR SAI SADAN CHS LTD” bearing registration number P51800002369, reg |
Located at BORIVALI EAST, BORIVALI EAST, Borivali, Mumbai Suburban, 400066. Per the filed land record, the plot is bounded to the north by adj cts 18 3 mt wide road, to the south by 2334 pt, to the east by adj cts 2334 4 and road and to the west by adj cts no 2396 5 2331 2B. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.
| Landmark | Straight-line |
|---|---|
| Andheri MIDC / SEEPZ | 11 km |
| Powai / Hiranandani business park | 13 km |
| Chhatrapati Shivaji Int'l Airport | 16 km |
| Bandra Kurla Complex (BKC) | 18 km |
| Lower Parel / Worli business district | 26 km |
| Nariman Point / Fort | 34 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in BLDG NO.1 DAHISAR SAI SADAN CHS LTD?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026