Mumbai/Project record

MahaRERA · the public record

BRAMHARAJ ANNEX

AIROLI · VIDHAATA DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700031486

Delivery and registration

When is the project declared for completion?

BRAMHARAJ ANNEX is registered with MahaRERA as P51700031486 and the promoter has declared completion for 31 Dec 2023.

31 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700031486
Registered on25 Oct 2021
Promoter-declared completion31 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for BRAMHARAJ ANNEX record 9 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 9 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for BRAMHARAJ ANNEX in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
BRAMHARAJ ANNEX1G+831 Dec 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2023IN INITIAL PHASES, CC WAS REVOKED AND THEN THE REVOCATION WAS CANCELLED. THERE WAS A DELAY IN GRANTING OF CERTAIN PERMISSIONS.
30 Jun 202331 Dec 2023The Building is ready. There is a delay in obtaining the Occupancy certificate from the department. We are in the process of obtaining the OC at the earliest.

Location, Land & Connectivity

Located at AIROLI, SECTOR-9, Thane, Thane, 400708. Per the filed land record, the plot is bounded to the north by 11MTR WIDE ROAD, to the south by PLOT NO F-66, to the east by SOCIETY PLOT NO 2 and to the west by PLOT NO F-64. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Airoli

Alliaance Galaxy
possession by Oct 2026 · Aashutosh Enterprise
Bramharaj Orchid
possession by Dec 2026 · Bramharaj Developers
ONE Pyramid
possession by Dec 2026 · Pacific Properties
Surbhi Sangeeta Co-Op. Housing Society Ltd
possession by Dec 2026 · Kumar & Kumar Builders LLP
Delta Luxuria
possession by Apr 2027 · Shreenathji Organisers PVT LTD
Delta Icon
possession by Jul 2027 · Shreenathji Organisers PVT LTD

Other RERA-registered projects in Thane

Bramharaj Orchid
possession by Dec 2026 · Bramharaj Developers
Breeze Heights
possession by Dec 2028 · Amore Builders LLP
Breeze One
possession by Dec 2030 · MM Breeze Realty LLP
Britto House
declared completion Dec 2018 · Shree SAI Builders & Developers
Broadway Annex
declared completion Jun 2024 · Ganesh Chandrakant Malvankar
Brothers Avenue
possession by Dec 2027 · Five Brothers Corporation

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026