Mumbai/Project record

MahaRERA · the public record

Callista

Andheri · JOY AND SAYLA REALTORS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800012448

Delivery and registration

When is the project declared for completion?

Callista is registered with MahaRERA as P51800012448 and the promoter has declared completion for 31 Dec 2024.

31 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800012448
Registered on01 Sep 2017
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Callista record 30 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 30 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Callista in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+19.

BuildingWingsFloorsDeclared completion
Callista1G+1931 Dec 2020

Legal and disputes

What disputes are disclosed?

6 complaints are on the MahaRERA record for Callista, with orders passed in 5 of them.

6complaints

5with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000017191319/12/2019Bharti Amitkumar Lathiya vs Charmi Nirmanorder passed
CC00600000039644330/06/2023Harsha Kumar Gowardhan vs Shri Bharat K Vaghasiyaorder passed
CC00600000039747613/09/2023KUNAL PANKAJ RAVAL vs JOY AND SAYLA REALTORSorder passed
CC00600000039788422/11/2023Gulabchand Tileshwarnath Mishra vs Joy and Sayla Realtorsorder passed
CC1240028630/09/2024Mitesh Rajnikant Shah vs JOY AND SAYLA REALTORSorder passed
CC1260230619/04/2026Callista Welfare Association vs JOY AND SAYLA REALTORSpending / no order on file

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
High Court101392013Pending

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2023The construction of sale Buildings is almost complete but some minor finishing works remained due to the area in which project is going on fall within a containment zone under
30 Jun 202331 Dec 2024The application for the extension of registration of the Project under Section 6 of the RERA read with the Rule 7 of the Maharashtra Real Estate (Regulation and Development) (Regis

Location, Land & Connectivity

Located at Andheri , Azad Road, Mumbai, Mumbai Suburban, 400069. Per the filed land record, the plot is bounded to the north by CTS No 82 - 83, to the south by CTS No 79, to the east by DP Road - WE highway and to the west by Rehab Building - CTS No 85. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Andheri MIDC / SEEPZ2 km
Chhatrapati Shivaji Int'l Airport4 km
Powai / Hiranandani business park5 km
Bandra Kurla Complex (BKC)6 km
Lower Parel / Worli business district14 km
Nariman Point / Fort22 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Andheri East

Anamika
possession by Sep 2026 · NEW India Constructions
Romell Myra
Deregistered by MahaRERA · possession by Sep 2026 · Romell Properties Private Limited
Romell Orbis
possession by Sep 2026 · Romell Properties Private Limited
Amey Apartments
possession by Oct 2026 · Amey Realty AND Construction LLP
Elegant Residency
possession by Dec 2026 · Elegant Builders AND Developers
Girnar Residency Wing B Phase 1
possession by Dec 2026 · Nidhaan Realty LLP

Major developers building in Andheri East

Other RERA-registered projects in Mumbai Suburban

Camaraderie CHS LTD
declared completion Dec 2023 · Mishal Construction Private Limited
Casa Bella
possession by Jun 2030 · Arth Developers
Casa Feliz
declared completion Aug 2019 · Karan Surender Saluja
Casa Palazzo
declared completion Feb 2022 · M/s. Paradigm Real Estates LLP
Casa Rare
declared completion Sep 2022 · Geopreneur Corp PVT LTD
Casa Varela
declared completion Mar 2019 · Swamikrupa Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026