CHANDRANGAN RESIDENCY PHASE - II

DIVA EAST · EKVEERA ENTERPRISES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700025153

Delivery and registration

When is the project declared for completion?

CHANDRANGAN RESIDENCY PHASE - II is registered with MahaRERA as P51700025153 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700025153
Registered on19 Mar 2020
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for CHANDRANGAN RESIDENCY PHASE - II record 16 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 16 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Ekveera Enterprises is the promoter of record on 18 projects registered with MahaRERA, 5 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

18projects

registered with MahaRERA

5flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for CHANDRANGAN RESIDENCY PHASE - II in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+21.

BuildingWingsFloorsDeclared completion
BUILDING - A1G+21-
BUILDING - B1G+21-
BUILDING - C1G+3-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at DIVA EAST, DIVA SHIL ROAD, NEAR KALPATARU JEWELLERS, Thane, Thane, 400612. Per the filed land record, the plot is bounded to the north by SR NO 63 PT, to the south by SIDDHI VINAYAK GARDEN CHS, to the east by CHANDRANGAN RESIDENCY PHASE 1 SR NO 70 6H and to the west by SR NO 69 7A AND 69 7B. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Ekveera Enterprises is the promoter on 9 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Ekveera Enterprises project & its RERA track record →

Other flagged projects by Ekveera Enterprises

Ekveera Enterprises
Not filing quarterly progress reportsThane

Other RERA-registered projects in Mumbra

Celosia Avenue
possession by Sep 2026 · Pratima Construction
Quality Annex
possession by Sep 2026 · Quality Annex
YES Central Galleria
possession by Oct 2026 · Noble Enterprises
YES Central Galleria 1
possession by Oct 2026 · YES Enterprises
Sagar Enclave
possession by Dec 2026 · Kanchan Builders & Developers
Grace Square Type D3
possession by Dec 2026 · Shree Sumatinath Enterprises LLP

Major developers building in Mumbra

Other RERA-registered projects in Thane

Chandrangan Residency Phase-IV
possession by Dec 2026 · Ekveera Enterprises
Chandrangan Residency Phase-V
possession by Dec 2027 · Ekveera Enterprises
Chandraprabha Heights
declared completion Mar 2023 · Pragalbha Construction
Chandraprabhakar Co-Operative Housing Society Limited
declared completion Apr 2025 · Mellennium Homes
Chandresh Terrace
possession by Dec 2033 · C9 Infra
Changuna Aangan
possession by Jun 2027 · Samrin Dreamspaces Private LTD

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.