30 Mar 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Mar 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700018175

Delivery and registration

When is the project declared for completion?

CHANDRAPRABHA HEIGHTS is registered with MahaRERA as P51700018175 and the promoter has declared completion for 30 Mar 2023.

30 Mar 2023

declared completion

42months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700018175
Registered on12 Oct 2018
Promoter-declared completion30 Mar 2023
Current statusCertificate Signed
Against todayabout 42 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for CHANDRAPRABHA HEIGHTS record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for CHANDRAPRABHA HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
CHANDRAPRABHA HEIGHTS1G+731 Mar 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at BALYANI, BALYANI, Kalyan, Thane, 421102. Per the filed land record, the plot is bounded to the north by RESERVATION NO 121 FOR CG, to the south by S NO 13, to the east by EXISTING ROAD and to the west by 24 MTRS WIDE DP ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ambivali West

Godrej Riviera Phase 1
possession by Dec 2026 · Godrej Properties Limited
Gaikwad Residency
possession by Dec 2026 · Niwara Group
Gangubai Height
possession by Dec 2026 · Vinayak Construction
Ashapura Galaxy
possession by Mar 2027 · Ashapura Estates
Lotus Residency
possession by Mar 2027 · Kulvinder Infrastructure Private Limited
Neptune Triveni Sangam
Developer in insolvency (NCLT) · possession by Jul 2027 · Neptune Developers Limited

Major developers building in Ambivali West

Other RERA-registered projects in Thane

Chandraprabhakar Co-Operative Housing Society Limited
declared completion Apr 2025 · Mellennium Homes
Chandresh Terrace
possession by Dec 2033 · C9 Infra
Changuna Aangan
possession by Jun 2027 · Samrin Dreamspaces Private LTD
Charms City A12
declared completion Jul 2024 · Charms Developers
Charms City B AND C Wing
possession by Dec 2028 · Charms Developers
Charms City Phase II
declared completion Dec 2025 · Gurukripa Landholding LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.