62units filed as unsoldInventory · 18 September 2026
16 Dec 2026declared completionMahaRERA registration · read 12 Jul 2026
1,021registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

16 Dec 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700032552

Delivery and registration

When is the project declared for completion?

Godrej Riviera Phase 1 is registered with MahaRERA as P51700032552 and the promoter has declared completion for 16 Dec 2026.

16 Dec 2026

declared completion

3months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700032552
Registered on11 Jan 2022
Promoter-declared completion16 Dec 2026
Current statusCertificate Signed
Against today3 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Godrej Riviera Phase 1 record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Godrej Properties is the promoter of record on 62 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

62projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In Godrej Riviera Phase 1, ₹213.71 Cr of a declared ₹268.48 Cr estimated project cost is reported as incurred, about 79.6%, as at the last certified filing with MahaRERA.

79.6%

₹213.71 Cr

of ₹268.48 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In Godrej Riviera Phase 1, 885 of 947 homes filed with MahaRERA are recorded as sold or booked (773 with registered agreements and 112 booked), about 93%, and 62 remain available.

93%sold

885 of 947 homes

₹440.62 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹131.19 Cr (about 30%) is recorded as collected and ₹309.42 Cr as receivable. The project registers 1,021 homes in total, while this sold/unsold inventory filing covers 947 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 885 registered agreements, the effective carpet rate is ₹11,741/sqft, with eight in ten falling between ₹9,998 and ₹13,339 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The inventory filing also declares: 74 not for sale.

What the filings record, home by home

Read from MahaRERA on 18 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 885 homes carry one, and 62 of the 1021 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
T21907413 sqftRs 47.06 lakh typical, over Rs 37.41 lakh to Rs 55.12 lakh80 filed on this stack, floors 1–22

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In Godrej Riviera Phase 1, 57 of the 62 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 61 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+22 and 1021 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
TOWER 11G+22253-
TOWER 21G+22263-
TOWER 31G+22255-
TOWER 41G+22250-

Unit mix on the filing: 942 residential and 79 non-residential (shops/offices).

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for Godrej Riviera Phase 1, with orders passed in 0 of them.

1complaint

0with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1250200319/06/2025NIPUN JAIN vs GODREJ PROPERTIES LIMITEDpending / no order on file

Location, Land & Connectivity

Located at Kalyan , 30 ft Mohane Road, Kurla, Mumbai Suburban, 421102. Per the filed land record, the plot is bounded to the north by Survey54A2and15mDPRoad, to the south by UlhasRiver, to the east by 30mDPRoad and to the west by Survey54A2. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Nariman Point / Fort4 km
Lower Parel / Worli business district5 km
Bandra Kurla Complex (BKC)13 km
Chhatrapati Shivaji Int'l Airport15 km
Powai / Hiranandani business park19 km
Andheri MIDC / SEEPZ20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Godrej Properties Limited is the promoter on 8 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Godrej Properties Limited project & its RERA track record →

Other flagged projects by Godrej Properties Limited

Godrej Properties Limited
FlaggedThane
Godrej Properties Limited
FlaggedMumbai Suburban
Godrej Properties Limited
FlaggedMumbai Suburban
Godrej Properties Limited
FlaggedMumbai Suburban
Godrej Properties Limited
FlaggedMumbai Suburban
Godrej Properties Limited
FlaggedMumbai Suburban

Other RERA-registered projects in Ambivali West

Gaikwad Residency
possession by Dec 2026 · Niwara Group
Gangubai Height
possession by Dec 2026 · Vinayak Construction
Ashapura Galaxy
possession by Mar 2027 · Ashapura Estates
Lotus Residency
possession by Mar 2027 · Kulvinder Infrastructure Private Limited
Neptune Triveni Sangam
Developer in insolvency (NCLT) · possession by Jul 2027 · Neptune Developers Limited
Neptune Swarajya 4B
Developer in insolvency (NCLT) · possession by Dec 2027 · Neptune Developers Limited

Major developers building in Ambivali West

Other RERA-registered projects in Thane

Godrej Upavan
possession by Jun 2028 · Prakhhyat Dwellings LLP
Godrej Vihaa Phase 5
possession by Dec 2031 · K. R. Real Estate Pvt. Ltd.
Gokul Park
possession by Dec 2030 · M/S Tiwari Enterprises
Gokul Vanrai
possession by Dec 2028 · M/s Mehul Enterprises
Gokul Villa
declared completion Jun 2023 · Greencity Infra
Gokuldham
possession by Dec 2028 · Maanit Infra

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026