GODREJ VIHAA PHASE 5

Mumbai City · K. R. REAL ESTATE PVT. LTD.

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2031declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2031

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700008346

Delivery and registration

When is the project declared for completion?

GODREJ VIHAA PHASE 5 is registered with MahaRERA as P51700008346 and the promoter has declared completion for 30 Dec 2031.

30 Dec 2031

declared completion

63months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700008346
Registered on18 Aug 2017
Promoter-declared completion30 Dec 2031
Current statusCertificate Signed
Against today63 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for GODREJ VIHAA PHASE 5 record 44 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for GODREJ VIHAA PHASE 5 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+1.

BuildingWingsFloorsDeclared completion
BUILDING NO 5B1G+1-
BUILDING NO 6B1G+1-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Ward ABCD, Mumbai City, 421502. Per the filed land record, the plot is bounded to the north by 5 by 7 PT 5 by 6 PT 6 by 1 PT, to the south by 7 by 2 PT Phase 2, to the east by 7 by 2 PT 7 by 1 PT 6 by 1 PT 5 by 6 PT Phase 3 and to the west by 7 by 9 PT 1 by 6 PT 5 by 8 PT 5 by 7 PT. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~36 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park36 km
Andheri MIDC / SEEPZ40 km
Chhatrapati Shivaji Int'l Airport41 km
Bandra Kurla Complex (BKC)41 km
Lower Parel / Worli business district47 km
Nariman Point / Fort51 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

K. R. Real Estate Pvt. Ltd. is the promoter on 4 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every K. R. Real Estate Pvt. Ltd. project & its RERA track record →

Other flagged projects by K. R. Real Estate Pvt. Ltd.

K. R. Real Estate Pvt. Ltd.
FlaggedThane

Other RERA-registered projects in Jawsai Gaon

Sky Gardens At Godrej Vihaa
possession by Sep 2026 · K. R. Real Estate Pvt. Ltd.
Sudama Elevate
possession by Dec 2026 · Sudam Zipa Rasal
Shree Ram Kutir
possession by May 2027 · Shreeram Realty
Vasudev Valley, Jamdare Heights
Not filing quarterly progress reports · possession by Mar 2028 · Ravindra Hari Gaikwad
Patels Pristine
possession by Jun 2031 · Sahajanand Developers
Leena Park
Past its declared completion date · declared completion Jun 2024 · Vasudha Developers

Other RERA-registered projects in Thane

Gokul Park
possession by Dec 2030 · M/S Tiwari Enterprises
Gokul Vanrai
possession by Dec 2028 · M/s Mehul Enterprises
Gokul Villa
declared completion Jun 2023 · Greencity Infra
Gokuldham
possession by Dec 2028 · Maanit Infra
Gold Crest
possession by May 2027 · Jay Ganesh Developers
Goldcrest Residency - Phase 1
declared completion Dec 2020 · Savita Homemakers LLP

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026