MahaRERA · the public record
NEPTUNE SWARAJYA 4B
Mumbai Suburban · NEPTUNE DEVELOPERS LIMITED
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
30 Dec 2027
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P51700009589
Delivery and registration
When is the project declared for completion?
NEPTUNE SWARAJYA 4B is registered with MahaRERA as P51700009589 and the promoter has declared completion for 30 Dec 2027.
30 Dec 2027
declared completion
15months to go
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P51700009589 |
| Registered on | 22 Aug 2017 |
| Promoter-declared completion | 30 Dec 2027 |
| Current status | Certificate Signed |
| Against today | 15 months to the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for NEPTUNE SWARAJYA 4B record 37 quarterly progress reports since registration.
37quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- NCLT / insolvency — the promoter is (or was) before the NCLT for insolvency — the gravest RERA flag; buyer money and possession are at real risk.
- Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).
Promoter record
What else is this promoter on record for?
Neptune Developers Limited is the promoter of record on 53 projects registered with MahaRERA, 52 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
53projects
registered with MahaRERA
52flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for NEPTUNE SWARAJYA 4B in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 12 Jul 2026
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+35.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| SECTOR 4B - 2 | 1 | G+35 | - |
| SECTOR 4B - 3 | 1 | G+35 | - |
| SECTOR 4B - 4 | 1 | G+35 | - |
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Location, Land & Connectivity
Located at Kurla, Mumbai Suburban, 421102. Per the filed land record, the plot is bounded to the north by S NO 87, to the south by S NOS 64 65, to the east by S NOS 90 and to the west by 30 M WIDE DP ROAD. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~35 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.
| Landmark | Straight-line |
|---|---|
| Powai / Hiranandani business park | 35 km |
| Andheri MIDC / SEEPZ | 37 km |
| Chhatrapati Shivaji Int'l Airport | 40 km |
| Bandra Kurla Complex (BKC) | 41 km |
| Lower Parel / Worli business district | 49 km |
| Nariman Point / Fort | 55 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.