Mumbai/Project record

MahaRERA · the public record

CHAVAN ADVAITAM

Near Sandip Hotel · SAIDEEP CONSTRUCTIONS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

122units filed as unsoldInventory · 19 September 2026
31 Dec 2026declared completionMahaRERA registration · read 12 Jul 2026
266registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700046731

Delivery and registration

When is the project declared for completion?

CHAVAN ADVAITAM is registered with MahaRERA as P51700046731 and the promoter has declared completion for 31 Dec 2026.

31 Dec 2026

declared completion

3months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700046731
Registered on01 Sep 2022
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today3 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for CHAVAN ADVAITAM record 15 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 15 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Saideep Constructions is the promoter of record on 3 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

3projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In CHAVAN ADVAITAM, ₹71.32 Cr of a declared ₹120.28 Cr estimated project cost is reported as incurred, about 59.3%, as at the last certified filing with MahaRERA.

59.3%

₹71.32 Cr

of ₹120.28 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In CHAVAN ADVAITAM, 114 of 236 homes filed with MahaRERA are recorded as sold or booked, about 48%, and 122 remain available.

48%sold

114 of 236 homes

₹97.19 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹51.46 Cr (about 53%) is recorded as collected and ₹44.72 Cr as receivable. The project registers 266 homes in total, while this sold/unsold inventory filing covers 236 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 114 registered agreements, the effective carpet rate is ₹11,577/sqft, with eight in ten falling between ₹9,580 and ₹13,818 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The inventory filing also declares: 8 reserved and 22 not for sale.

What the filings record, home by home

Read from MahaRERA on 19 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 114 homes carry one, and 122 of the 266 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
2807691 sqftRs 80.00 lakh typical, over Rs 60.05 lakh to Rs 97.84 lakh19 filed on this stack, floors 9–27

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In CHAVAN ADVAITAM, 93 of the 122 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 121 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+33 and 266 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
BUILDING NO 1 ADVAITAM PLAZA/VILLAMENT1G+33264-
BUILDING NO 2 AVAITAM HEIGHTS1G+01-
BUILDING NO 3 BUNGLOW1G+01-

Unit mix on the filing: 230 residential and 36 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Distric Judge Kayan72020Pending

Location, Land & Connectivity

Located at Near Sandip Hotel, Bhiwandi Murbad Highway, Kalyan, Thane, 421301. Per the filed land record, the plot is bounded to the north by Sai Sitaram Residency, to the south by Morya Hospital, to the east by 12 M wide Layout Road and to the west by 30 M wide D P Road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~29 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park29 km
Andheri MIDC / SEEPZ32 km
Chhatrapati Shivaji Int'l Airport34 km
Bandra Kurla Complex (BKC)35 km
Lower Parel / Worli business district43 km
Nariman Point / Fort49 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kalyan

Bhushan Anand CO OP HSG SOC
possession by Sep 2026 · Dinesh Laxman Sonavane
Ishanvi Ashapura Tower
possession by Sep 2026 · Ishanvi Ashapura Developers
Keshar Aagan Cooperative Housing Society
possession by Sep 2026 · Gagan Homes
Mohan Deep
possession by Sep 2026 · Sunil Purushottam Deshmukh
Parshuram Tower
possession by Sep 2026 · Moreshwar Constructions
Ritz Phase II Commercial Tower D
possession by Sep 2026 · Vikas Harakchand Jain

Major developers building in Kalyan

Other RERA-registered projects in Thane

Chavan Elegance
declared completion Mar 2024 · Anjana Sahebrao Chavan
Chavan Sarveshwara
possession by Jun 2029 · Not Available
Chavan Star
declared completion Jul 2026 · Not Available
Cherivali Hills
declared completion Dec 2019 · Dhariwal Khabia Developers LLP
Chhaya Central Greens
possession by Mar 2032 · Not Available
Chintamani Cooperative Housing Society LTD
declared completion Apr 2022 · Utkarsha Construction

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026