Mumbai/Project record

MahaRERA · the public record

CHINTAMANI HEIGHTZ

Cherpoli · JASHNANI CONSTRUCTION PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

200units filed as unsoldInventory · 20 September 2026
31 Dec 2030declared completionMahaRERA registration · read 12 Jul 2026
239registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2030

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · PR1330002501955

Delivery and registration

When is the project declared for completion?

CHINTAMANI HEIGHTZ is registered with MahaRERA as PR1330002501955 and the promoter has declared completion for 31 Dec 2030.

31 Dec 2030

declared completion

51months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationPR1330002501955
Registered on30 Dec 2025
Promoter-declared completion31 Dec 2030
Current statusCertificate Signed
Against today51 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for CHINTAMANI HEIGHTZ record 2 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 2 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Jashnani Construction is the promoter of record on 11 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

11projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In CHINTAMANI HEIGHTZ, ₹1.18 Cr of a declared ₹36.58 Cr estimated project cost is reported as incurred, about 3.2%, as at the last certified filing with MahaRERA.

3.2%

₹1.18 Cr

of ₹36.58 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In CHINTAMANI HEIGHTZ, 0 of 200 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 200 remain available.

0%sold

0 of 200 homes

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. The project registers 239 homes in total, while this sold/unsold inventory filing covers 200 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

The inventory filing also declares: 84 owner/investor-held.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for CHINTAMANI HEIGHTZ in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 20 September 2026

What the filings record, home by home

Read from MahaRERA on 20 September 2026

No home in CHINTAMANI HEIGHTZ carries a registered agreement value on its MahaRERA filing, so there is no record here of what anyone has paid. What the promoter has filed is the government ready reckoner value for 284 homes — the Annual Statement of Rates valuation, with each home’s carpet area and floor already applied. Across them that is Rs 5,017 a sq ft typical, over Rs 5,017 to Rs 6,039.

A reckoner value is the basis stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home to you.

The Reckoner Record lists all 284 of them — each home, its RERA carpet area, the valuation filed against it and the rate that works out to. It is the filing copied, not a reading of it.

See all 284 filed valuations — ₹999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8 and 239 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Chintamani Heightz Type A1G+8102-
Chintamani Heightz Type B1G+768-
Chintamani Heightz Type C2G+769-

Unit mix on the filing: 274 residential and 10 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Cherpoli, Gut No 123/125, Thane, Thane, 421601. Per the filed land record, the plot is bounded to the north by As per the approved drawing/layout attached, to the south by As per the approved drawing/layout attached, to the east by As per the approved drawing/layout attached and to the west by As per the approved drawing/layout attached. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~58 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park58 km
Andheri MIDC / SEEPZ60 km
Chhatrapati Shivaji Int'l Airport63 km
Bandra Kurla Complex (BKC)65 km
Lower Parel / Worli business district73 km
Nariman Point / Fort79 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Jashnani Construction Private Limited is the promoter on 11 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Jashnani Construction Private Limited project & its RERA track record →

Other flagged projects by Jashnani Construction Private Limited

Jashnani Construction Private Limited
FlaggedThane
Jashnani Construction Private Limited
FlaggedThane
Jashnani Construction Private Limited
FlaggedThane

Other RERA-registered projects in Shahapur

Awasare Heights
possession by Sep 2026 · Rajkumar Tuljaram Aswani
Krishna Crown
possession by Oct 2026 · Shree Krishna Reality
Sava Arcade
possession by Oct 2026 · Sava Developers
Shantaram Park Residency
possession by Dec 2026 · Shubha Developers
Darshan Ganesh Apartment
possession by Dec 2026 · Tirupati Construction
Chintamani Meadows
possession by Dec 2026 · Jashnani Construction Private Limited

Major developers building in Shahapur

Other RERA-registered projects in Thane

Chintamani Meadows
possession by Dec 2026 · Jashnani Construction Private Limited
Chintamani Park
declared completion Dec 2022 · Shree Vallabh Realities
Chintamani Plaza
declared completion Dec 2024 · Jashnani Construction Private Limited
Chirag Construction
declared completion Aug 2022 · Chirag Gajanan Patil
Choice Ambe Deep
declared completion Dec 2018 · Ambe Deep Enterprises
City Centre
possession by Mar 2028 · Kinikar Multipurpose Hospital

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026