Mumbai/Project record

MahaRERA · the public record

CHOICE AMBE DEEP

Sanpada · AMBE DEEP ENTERPRISES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2018declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700002104

Delivery and registration

When is the project declared for completion?

CHOICE AMBE DEEP is registered with MahaRERA as P51700002104 and the promoter has declared completion for 31 Dec 2018.

31 Dec 2018

declared completion

93months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700002104
Registered on31 Jul 2017
Promoter-declared completion31 Dec 2018
Current statusCertificate Signed
Against todayabout 93 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for CHOICE AMBE DEEP record 6 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 6 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Ambe Deep Enterprises is the promoter of record on 89 projects registered with MahaRERA, 13 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

89projects

registered with MahaRERA

13flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for CHOICE AMBE DEEP in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
CHOICE AMBE DEEP1G+8-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Panvel Court102/20082008Hereing

Location, Land & Connectivity

Located at Sanpada, Thane, Thane, 400705. Per the filed land record, the plot is bounded to the north by PLOT NO 135, to the south by PLOT NO 133, to the east by PLOT NO 129 AND 130 and to the west by 22 MTR WIDE ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~20 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Nariman Point / Fort16 km
Lower Parel / Worli business district20 km
Bandra Kurla Complex (BKC)24 km
Chhatrapati Shivaji Int'l Airport26 km
Powai / Hiranandani business park28 km
Andheri MIDC / SEEPZ30 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Sanpada

ONE Akshar
possession by Dec 2026 · Akshar Realtors
Raheja Solaris-1
possession by Dec 2026 · Raheja Universal Ltd.
BUL BUL CO-Operative Housing Society Limited
possession by Dec 2026 · Ashwiniinfradevelopments Private Limited
Gami Terra
possession by Dec 2026 · LAL Gebi Infra Private Limited
Satyam Altura
possession by Dec 2026 · Satyam Lifescapes LLP
Tricity Montview
possession by Dec 2026 · Tricity Realty LLP

Major developers building in Sanpada

Other RERA-registered projects in Thane

City Centre
possession by Mar 2028 · Kinikar Multipurpose Hospital
City Pride
declared completion Dec 2019 · City Pride Incorporation
City Pride NX
possession by Mar 2030 · Abhishek Buildcon
Classic Plaza
possession by Dec 2028 · NEW Classic Construction
Classic Residency
declared completion Jun 2021 · Classic Construction
Code Name-Enchanted
possession by Jun 2028 · Runwal Construction Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026