COLONEL CHSLCOMMANDER CHSLAND

NALLA SOPARA WEST · SHREE BALAJI ENTERPRISES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000018540

Delivery and registration

When is the project declared for completion?

COLONEL CHSLCOMMANDER CHSLAND is registered with MahaRERA as P99000018540 and the promoter has declared completion for 30 Dec 2024.

30 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000018540
Registered on13 Nov 2018
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for COLONEL CHSLCOMMANDER CHSLAND record 25 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 25 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for COLONEL CHSLCOMMANDER CHSLAND in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+24.

BuildingWingsFloorsDeclared completion
COLONEL BUILDING1G+1331 Dec 2021
COMMANDER BLDG1G+2431 Dec 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at NALLA SOPARA WEST, MORE VILLAGE, Vasai, Palghar, 401209. Per the filed land record, the plot is bounded to the north by PLOT NO 14, to the south by PLOT NO 11, to the east by ROAD and to the west by RAIL TRACK. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shree Balaji Enterprises is the promoter on 10 MahaRERA-registered projects, of which 4 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Shree Balaji Enterprises project & its RERA track record →

Other flagged projects by Shree Balaji Enterprises

Shree Balaji Enterprises
FlaggedPalghar
Shree Balaji Enterprises
Past its declared completion datePalghar

Other RERA-registered projects in Nallasopara East

Model Cooperative Housing Society LTD
possession by Oct 2026 · Sai Vaishnav Infra Llp
N G Platinum City
possession by Dec 2026 · J M G Realtors PVT LTD
Rudra Heights Bldg NO 1 Wing -G
possession by Dec 2026 · Aura Navkar Developers
Ajay CO-Operative Housing Society LTD
possession by Dec 2026 · MAA Guru Construction
Imperialparamount
possession by Dec 2026 · Shivganga Construction & Redeveloper
Precilla CHS LTD
possession by Dec 2026 · Blue OAK Infrastructure

Other RERA-registered projects in Palghar

Colours City
declared completion Dec 2024 · Sugandhi Enterprises
Colours Pride
declared completion Dec 2024 · Colours Enterprises
Comfort Avenue
possession by Dec 2027 · Comfort Realtors
Comfort Empire
possession by Dec 2029 · Sunrise Developers
Comfort Heritage
possession by Dec 2029 · SAI Rydam Real Estate Developers LLP
Comfort View
declared completion Dec 2025 · Comfort Infratech

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.