Coral Bay
Bagmala · Dynamix Vacation Resorts Private Limited
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 02 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
31 Dec 2028
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 02 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · PP1270002600903
Delivery and registration
When is the project declared for completion?
Coral Bay is registered with MahaRERA as PP1270002600903 and the promoter has declared completion for 31 Dec 2028.
31 Dec 2028
declared completion
27months to go
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 02 Jul 2026
| MahaRERA registration | PP1270002600903 |
| Registered on | 23 Jun 2026 |
| Promoter-declared completion | 31 Dec 2028 |
| Current status | Certificate Signed |
| Against today | 27 months to the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Coral Bay record 1 quarterly progress report since registration.
1quarterly filing
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 02 Jul 2026
- Filing progress reports — 1 quarterly progress report on record since registration, with no current default.
Promoter record
What else is this promoter on record for?
Dynamix Vacation Resorts is the promoter of record on 8 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
8projects
registered with MahaRERA
0flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 02 Jul 2026
Construction
How much construction cost has been reported?
In Coral Bay, ₹0 of a declared ₹22.94 Cr estimated project cost is reported as incurred, about 0.0%, as at the last certified filing with MahaRERA.
0.0%
₹0
of ₹22.94 Cr declared cost
Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.
Source · MahaRERA quarterly progress filing · read 02 Jul 2026
Sales
How much has actually been sold?
In Coral Bay, 0 of 70 plots filed with MahaRERA are recorded as sold or booked, about 0%, and 70 remain available.
0%sold
0 of 70 plots
Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.
Source · MahaRERA sold/unsold inventory filing · read 02 Jul 2026
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for Coral Bay in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 16 September 2026
What the filings record, plot by plot
Read from MahaRERA on 16 September 2026
No plot in Coral Bay carries a registered agreement value on its MahaRERA filing, so there is no record here of what anyone has paid. What the promoter has filed is the government ready reckoner value for 70 plots — the Annual Statement of Rates valuation, with each plot’s filed area already applied. Across them that is Rs 164 a sq ft typical, over Rs 164 to Rs 164.
A reckoner value is the basis stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the plot to you.
The Reckoner Record lists all 70 of them — each plot, its filed area, the valuation filed against it and the rate that works out to. It is the filing copied, not a reading of it.
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Location, Land & Connectivity
Located at Bagmala, RZ/05, gut No. 3/1/8.9.10, 270/1 and 35/1/2 Under ITP , Kurla, Mumbai Suburban, 402204. Per the filed land record, the plot is bounded to the north by RZ-06 & N.I.P. Land, to the south by N.I.P. land 35(p) & 38, to the east by N.I.P Land and to the west by Road. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~40 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.
| Landmark | Straight-line |
|---|---|
| Nariman Point / Fort | 32 km |
| Lower Parel / Worli business district | 40 km |
| Bandra Kurla Complex (BKC) | 48 km |
| Chhatrapati Shivaji Int'l Airport | 50 km |
| Powai / Hiranandani business park | 53 km |
| Andheri MIDC / SEEPZ | 55 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.