Crystal Residency

Nallasopara East · Sai Crystal Homes

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000047067

Delivery and registration

When is the project declared for completion?

Crystal Residency is registered with MahaRERA as P99000047067 and the promoter has declared completion for 30 Dec 2024.

30 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000047067
Registered on29 Sep 2022
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Crystal Residency record 10 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 10 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sai Crystal Homes is the promoter of record on 62 projects registered with MahaRERA, 8 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

62projects

registered with MahaRERA

8flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Crystal Residency in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
A Wing1G+331 Dec 2023
B Wing1G+331 Dec 2023
C Wing1G+331 Dec 2023
D Wing1G+331 Dec 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2024Building is almost completed waiting for Occupation Certificate Kindly Grant initial Extension. , Compliances as on 31.12.2023 is done and the copy of relevant certificates are als

Location, Land & Connectivity

Located at Nallasopara East, Achole Village, Taluka Vasai, Dist Palghar, Vasai, Palghar, 401209. Per the filed land record, the plot is bounded to the north by 40 M W D P Road, to the south by S No 219 and 220, to the east by 5 mtr and 6 m w Existing Road and to the west by 20 m w D P Road and S N 222. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~31 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ31 km
Powai / Hiranandani business park33 km
Chhatrapati Shivaji Int'l Airport36 km
Bandra Kurla Complex (BKC)38 km
Lower Parel / Worli business district46 km
Nariman Point / Fort54 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Nallasopara East

Model Cooperative Housing Society LTD
possession by Oct 2026 · Sai Vaishnav Infra Llp
N G Platinum City
possession by Dec 2026 · J M G Realtors PVT LTD
Rudra Heights Bldg NO 1 Wing -G
possession by Dec 2026 · Aura Navkar Developers
Ajay CO-Operative Housing Society LTD
possession by Dec 2026 · MAA Guru Construction
Imperialparamount
possession by Dec 2026 · Shivganga Construction & Redeveloper
Precilla CHS LTD
possession by Dec 2026 · Blue OAK Infrastructure

Other RERA-registered projects in Palghar

Crystal Tower
possession by Dec 2028 · Zenith Developers
D K Residency
possession by Dec 2028 · Kshipra Realty
Damodar Park C Bldg
possession by Dec 2029 · Parshwanath Developers
Dandekars Gandhakosh
possession by Aug 2027 · Jayant Vishnu Dandekar
Dange Chawre Crown B Wing
possession by May 2027 · Dange Developers
Dange Serenity
possession by Mar 2029 · United Realtors

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.