MahaRERA Property Intelligence · Raigarh

Dattvatsalya Apartment

P52000021126 · Node Pushpak (New) · promoter Sanjay Ramchandra Gaikwad

Certificate SignedDue 28 Nov 2022

Delivery & Registration

MahaRERA registrationP52000021126
Registered on03 Jun 2019
Promoter-declared completion28 Nov 2022
Current statusCertificate Signed
Against todayabout 44 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Sanjay Ramchandra Gaikwad is the promoter of record on 147 projects, of which 24 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
Dattvatsalya Apartment1G+430 Nov 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Node Pushpak (New), Plot no 324, Sector 24, Panvel, Raigarh, 400706. Per the filed land record, the plot is bounded to the north by Plot no 325, to the south by 9 meter wide road, to the east by 11 meter wide road and to the west by Plot no 321. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Nerul

Vishv Eleanor
possession by Aug 2026 · Vishv Realty
Cyber Code
possession by Sep 2026 · Greenscape Realty
Shreeji Dios
possession by Dec 2026 · Shreeji Ventures Nirmaan Private Limited
Infinity Ikon
possession by Dec 2026 · Emperia Projects
Plan I
possession by Dec 2026 · M/s. Tescon Plan-I LLP
Regency Palms Phase IV
possession by Dec 2026 · Regency INC

Other RERA-registered projects in Raigarh

Dbafna ONE
possession by Mar 2029 · D Bafna Properties
Ddsr Anuparva CO-Operative Housing Society Limited
possession by Dec 2027 · Ddsr Anuparva Co-Operative Housing Socie
Ddsr Heights
possession by Dec 2026 · Ddsr Builders And Developers LLP
Ddsr Heritage CHS LTD
possession by Dec 2028 · Ddsr Heritage CHS LTD
Ddsr Satvic
declared completion Mar 2026 · Ddsr Builders And Developers LLP
Deccan Pride
possession by Mar 2030 · Praveen Premkumar Nair

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.