MahaRERA Property Intelligence · Mumbai Suburban

Devtaa Pratham

P51800050716 · Goregaon West · promoter Vipul Mitra Co-Operative

Certificate SignedDue 15 Dec 2026

Delivery & Registration

MahaRERA registrationP51800050716
Registered on28 Apr 2023
Promoter-declared completion15 Dec 2026
Current statusCertificate Signed
Against today5 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Vipul Mitra Co-Operative is the promoter of record on 113 projects, of which 11 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~64.6% of the estimated project cost incurred as of the last certificate (₹17.34 Cr spent against a ₹26.85 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 25 homes filed with MahaRERA, 19 are sold/booked and 6 remain available (~76% sold) — selling steadily. Buyers have committed ₹29.71 Cr in agreement value so far. Of that, ₹21.32 Cr (~72%) is already collected, ₹8.39 Cr receivable — a read on how far along these sales really are. Note: the project registers 59 homes in total, but this sold/unsold inventory filing covers only 25 of them — the other 34 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 19 registered agreements, the effective carpet rate is ₹20,793/sqft (typical range ₹17,991–₹25,492) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 141402800 sqft (74.36 sqm)₹1.17 Cr
Floor 161604675 sqft (62.73 sqm)₹98.68 Lakh
Floor 171702800 sqft (74.36 sqm)₹98.68 Lakh
Floor 3301750 sqft (69.72 sqm)₹1.10 Cr
Floor 5502800 sqft (74.36 sqm)₹1.17 Cr
Floor 7702800 sqft (74.36 sqm)₹1.17 Cr

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+20 and 59 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Devtaa Pratham1G+2059-

Unit mix on the filing: 59 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Goregaon West , Pragati Nagar, Mumbai, Mumbai Suburban, 400062. Per the filed land record, the plot is bounded to the north by CTS 209F 209B 209E, to the south by CTS 217, to the east by CTS 207 and to the west by CTS 216. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Powai / Hiranandani business park6 km
Andheri MIDC / SEEPZ8 km
Chhatrapati Shivaji Int'l Airport11 km
Bandra Kurla Complex (BKC)13 km
Lower Parel / Worli business district22 km
Nariman Point / Fort29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Goregaon West

Modirealty Vatvriksh
possession by Sep 2026 · Modirealty Developers PVT LTD
Manju Villa
possession by Dec 2026 · Meghna Developers AOP
Nirlon Employees CHS LTD Building NO. 10
possession by Dec 2026 · Shivam Parivar Developers Private Limite
Happy Home Enclave
possession by Dec 2026 · JD & FC Ventures LLP
Laxmi Leela Arhum
possession by Dec 2026 · Laxmi Leela Constructions LLP
Navkar Ashray
Not filing quarterly progress reports · possession by Dec 2026 · Navkar Builder & Devvelopers

Major developers building in Goregaon West

Other RERA-registered projects in Mumbai Suburban

DGS Heights
possession by Dec 2026 · D.g.builders
Dhan Narain
possession by Dec 2028 · Starwing Developers Private Limited
Dhanishtha
possession by Dec 2030 · Ameya Realtors Private Limited
Dhanraj
declared completion Feb 2025 · Aneisha Livings LLP
Dhanraj Tower
possession by Jun 2027 · Govindrajulu Papa Naidu
Dhara Landspace
declared completion Mar 2023 · Dhara Landspace LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026