Mumbai/Project record

MahaRERA · the public record

DHARA LANDSPACE

Mumbai Suburban · DHARA LANDSPACE LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Mar 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Mar 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800012087

Delivery and registration

When is the project declared for completion?

DHARA LANDSPACE is registered with MahaRERA as P51800012087 and the promoter has declared completion for 30 Mar 2023.

30 Mar 2023

declared completion

42months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800012087
Registered on01 Sep 2017
Promoter-declared completion30 Mar 2023
Current statusCertificate Signed
Against todayabout 42 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for DHARA LANDSPACE record 23 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 23 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Dhara Landspace Llp is the promoter of record on 4 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

4projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for DHARA LANDSPACE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
ARIHANT ENCLAVE1G+14-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Kurla, Mumbai Suburban, 400086. Per the filed land record, the plot is bounded to the north by DELIGHT PALACE, to the south by SAGAR PLAZA, to the east by M G ROAD and to the west by IRANI BUNGALOW. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Powai / Hiranandani business park3 km
Chhatrapati Shivaji Int'l Airport4 km
Bandra Kurla Complex (BKC)5 km
Andheri MIDC / SEEPZ6 km
Lower Parel / Worli business district13 km
Nariman Point / Fort20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ghatkopar West

O AND S Royale
possession by Dec 2026 · Suchita Orange Project Royale
Sarvonnati CHS LTD
Deregistered by MahaRERA · possession by Dec 2026 · JAI Enterprises
Vighneshwar Cooperative Housing Society Limited
possession by Dec 2026 · Vighneshwar Coop Housing Society Limited
Arihant Heights
possession by Dec 2026 · Arihant Infrastructure Company
Avani Signature
possession by Dec 2026 · Avani Buildcon
Sanghvi Parsssva Jivdaya
possession by Dec 2026 · Sanghvi Constructions

Other RERA-registered projects in Mumbai Suburban

Dharti Pressidio
declared completion Dec 2025 · Milan Nemji Gala
Dhaval Chsl
declared completion May 2025 · Shree Ranchod Developers
Dhoot Adi Residency-Shree Adi House Chsl
declared completion Dec 2019 · Dhoot Developers Pvt. Ltd.
Dhoot Pride Residency-Devidayal Apartment
possession by Dec 2026 · Dhoot Developers Pvt. Ltd.
Dhoot Sapphire Residency
possession by Dec 2028 · Dhoot Developers Pvt. Ltd.
Dhoot Sky Residency-New Sonali Chsl
declared completion Dec 2022 · Dhoot Developers Pvt. Ltd.

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026