MahaRERA · the public record
Dhaval CHSL
Malad West · Shree Ranchod Developers
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
31 May 2025
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P51800046109
Delivery and registration
When is the project declared for completion?
Dhaval CHSL is registered with MahaRERA as P51800046109 and the promoter has declared completion for 31 May 2025.
31 May 2025
declared completion
16months past
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P51800046109 |
| Registered on | 20 Jun 2022 |
| Promoter-declared completion | 31 May 2025 |
| Current status | Certificate Signed |
| Against today | about 16 months past the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Dhaval CHSL record 13 quarterly progress reports since registration.
13quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).
Promoter record
What else is this promoter on record for?
Shree Ranchod Developers is the promoter of record on 6 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
6projects
registered with MahaRERA
3flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for Dhaval CHSL in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 12 Jul 2026
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| Dhaval CHSL | 1 | G+13 | 31 May 2025 |
Legal and disputes
What disputes are disclosed?
2 complaints are on the MahaRERA record for Dhaval CHSL, with orders passed in 1 of them.
2complaints
1with an order
Counts as disclosed in the project record.
Source · MahaRERA project disclosures · read 12 Jul 2026
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC12500622 | 22/02/2025 | Shree Ranchod Developers vs Harshala Jayendra Raut | pending / no order on file |
| CC12501191 | 09/04/2025 | Harshala Jayendra Raut vs Shree Ranchod Developers | order passed |
Location, Land & Connectivity
Located at Malad West, N L Cross Road, Mumbai, Mumbai Suburban, 400064. Per the filed land record, the plot is bounded to the north by Rikin CHSL, to the south by Mili CHSL, to the east by N L Cross Road and to the west by Siddhivinayak Enclave CHSL. These are the boundaries as recorded in the filed land record.