MahaRERA Property Intelligence · Mumbai Suburban

DHARMAPRATAP CHS LTD

P51800006987 · promoter Sai Life Realtors

Certificate SignedDue 30 Mar 2019

Delivery & Registration

MahaRERA registrationP51800006987
Registered on17 Aug 2017
Promoter-declared completion30 Mar 2019
Current statusCertificate Signed
Against todayabout 88 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
DHARMAPRATAP CHS LTS1G+13-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Kurla, Mumbai Suburban, 400077. Per the filed land record, the plot is bounded to the north by PLOT NO 75, to the south by PLOT NO 81, to the east by PLOT NO 67 AND 68 and to the west by BY ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Bandra Kurla Complex (BKC)4 km
Chhatrapati Shivaji Int'l Airport4 km
Powai / Hiranandani business park4 km
Andheri MIDC / SEEPZ7 km
Lower Parel / Worli business district12 km
Nariman Point / Fort19 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ghatkopar East

Baldevsingh Thakur SRA Coop HSG SOC LTD
possession by Jul 2026 · Krishna Narsingrao Pimple
Palatina
possession by Jul 2026 · Tanishq Builders
Vihar Heights
possession by Aug 2026 · Saptrishi Homes LLP
Poonam Celeste
possession by Aug 2026 · PL7 Realty Pvt. Ltd.
Hema Apartments CO-Operative Housing Society Limited
possession by Sep 2026 · Hema Appartments CO-Operative Housing So
Centrona ZEN-A
possession by Dec 2026 · Elevated Avenue Realty LLP

Major developers building in Ghatkopar East

Other RERA-registered projects in Mumbai Suburban

Dharti Pressidio
declared completion Dec 2025 · Milan Nemji Gala
Dharti SRA
declared completion Dec 2017 · Milan Nemji Gala
Dhaval Chsl
declared completion May 2025 · Shree Ranchod Developers
Dhiren CO Operative Housing Society
declared completion Dec 2018 · Utkarsh Construction
Dhoot Adi Residency-Shree Adi House Chsl
declared completion Dec 2019 · Dhoot Developers Pvt. Ltd.
Dhoot Emrald Residency-Jaygun Sagar Chsl
declared completion Mar 2018 · Dhoot Developers Pvt. Ltd.

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026