DREAM HOUSE

MURBAD · M S CONSTRUCTION

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700032989

Delivery and registration

When is the project declared for completion?

DREAM HOUSE is registered with MahaRERA as P51700032989 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700032989
Registered on03 Feb 2022
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for DREAM HOUSE record 16 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for DREAM HOUSE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
DREAM HOUSE1G+531 Dec 2025

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for DREAM HOUSE, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1250078307/03/2025Tushar Kamlakar Chaturya vs M S CONSTRUCTIONorder passed

Location, Land & Connectivity

Located at MURBAD, MURBAD, Thane, Thane, 421401. Per the filed land record, the plot is bounded to the north by S NO 283 3 PART, to the south by MALI PADA ROAD, to the east by MALI PADA ROAD and to the west by S NO 283 2 PART. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Murbad

Shree Siddhivinayak Park C1,c2,c3
Not filing quarterly progress reports · possession by Dec 2026 · Satyashiv Developers
Arjun Heights
Not filing quarterly progress reports · possession by Dec 2026 · Nanda Arjun Shelke
Madhusudan Retreat Terraces
possession by Dec 2026 · Madhusudan Leisure Homes
SAI Krishna Heights
possession by Dec 2026 · OM SAI Developers
Swami Narendra Residency
possession by Dec 2026 · RAJ Ratneshwari Developers
Techcons Basera
possession by Dec 2026 · Techcons Constructional Engineering Co

Other RERA-registered projects in Thane

Dream Ikon
possession by Dec 2027 · Dream Ikon Realtors
Dream Land
possession by Jun 2029 · Golden Triangle Builders & Developer
Dream Nexus
possession by Apr 2029 · Dream Constructions
Dream Nityanand
possession by Dec 2028 · Dream Constructions
Dream Paradise
possession by Dec 2027 · Pridedream Realtors
Dream Pragati
possession by Dec 2028 · Empire Horizons Private Limited

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026