Mumbai/Project record

MahaRERA · the public record

DURVANKUR

Thane · SAMEER MUKUND NATU

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900011548

Delivery and registration

When is the project declared for completion?

DURVANKUR is registered with MahaRERA as P51900011548 and the promoter has declared completion for 30 Dec 2021.

30 Dec 2021

declared completion

57months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900011548
Registered on31 Aug 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 57 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for DURVANKUR record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sameer Mukund Natu is the promoter of record on 33 projects registered with MahaRERA, 10 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

33projects

registered with MahaRERA

10flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for DURVANKUR in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+21.

BuildingWingsFloorsDeclared completion
Durvankur A wing1G+21-
Durvankur B wing1G+15-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for DURVANKUR, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1250016818/01/2025RUPARAM PRAGAJI CHOUDHARY vs SAMEER MUKUND NATUorder passed

Legal & Litigation

The promoter has declared 3 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Small Causes CourtRAD 20172011Hearing Is Pending
Joint Charity Commissioner1772016Hearing Is Pending
Joint Charity Commissioner012011Hearing Is Pending

Location, Land & Connectivity

Located at Thane, Thane, 400004. Per the filed land record, the plot is bounded to the north by VP Road, to the south by Sadashiv Cross Lane, to the east by CS no 494 and to the west by CS no 496. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Nariman Point / Fort4 km
Lower Parel / Worli business district5 km
Bandra Kurla Complex (BKC)13 km
Chhatrapati Shivaji Int'l Airport15 km
Andheri MIDC / SEEPZ20 km
Powai / Hiranandani business park20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Girgaum

Aaditya Residences
possession by Dec 2026 · M/s. A.k. Developers
Shreepati Bayview
Deregistered by MahaRERA · possession by Dec 2026 · Shreepati Build Infra Investment Limited
NEO Amity
possession by Dec 2026 · Naresh Kesarimal Mehta
Onyx
possession by Dec 2026 · Naminath Erector And Developers LLP
Promesa Castor
possession by Dec 2026 · Darshan Group
Raajdeep Arcade
possession by Dec 2026 · Raajdeep Builders AND Developers

Other RERA-registered projects in Mumbai City

Dvayam
possession by Dec 2029 · Kabra Estate AND Investment Consultants
Earth 280
possession by Aug 2027 · Earth Builders
Earth Anand
declared completion May 2025 · M/s. Earth Graphics
Earth Classic
declared completion Dec 2017 · Earthclassic
Earth Enclave
possession by Dec 2027 · Earth Graphics
Earth Vintage
declared completion Jun 2025 · Earth Vintage

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026