MahaRERA Property Intelligence · Raigarh

Eden Apartment

P52000032152 · Vadghar Pushpak Node · promoter Tushar Ramchandra Patil

Certificate SignedDue 31 Jan 2025

Delivery & Registration

MahaRERA registrationP52000032152
Registered on14 Dec 2021
Promoter-declared completion31 Jan 2025
Current statusCertificate Signed
Against todayabout 18 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Tushar Ramchandra Patil is the promoter of record on 147 projects, of which 24 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
Eden Apartment1G+531 Dec 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 3 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 202131 Jan 2025delay in procuring noc from cidco
31 Dec 202131 Dec 2023delay in procurement of noc for oc
31 Dec 202131 Dec 2022Rera Certificate was applied in month of september and was issued recently , so flats are not registered to buyers and hence there is a delay in procuring funds from the bank in co

Location, Land & Connectivity

Located at Vadghar Pushpak Node, Sector R3 Plot no 301, Panvel, Raigarh, 410206. Per the filed land record, the plot is bounded to the north by 9 meter Road, to the south by 305, to the east by 300 and to the west by 302. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~25 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park25 km
Bandra Kurla Complex (BKC)25 km
Chhatrapati Shivaji Int'l Airport27 km
Lower Parel / Worli business district28 km
Andheri MIDC / SEEPZ29 km
Nariman Point / Fort29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Tushar Ramchandra Patil is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Tushar Ramchandra Patil

Tushar Ramchandra Patil
FlaggedRaigarh

Other RERA-registered projects in Panvel

Ambaji Residency
possession by Jul 2026 · Vishal Tukaram Patil
Bayview
possession by Jul 2026 · Skyline Realbuild LLP
Delta Heights
possession by Jul 2026 · Shreenathji Organisers Pvt. Ltd.
Micron Residency
possession by Jul 2026 · Micron Infra
Shree Mahadev Residency
possession by Jul 2026 · SK Developers
Aishwarya Cooperative Housing Society
possession by Aug 2026 · Royal Enterprises

Major developers building in Panvel

Other RERA-registered projects in Raigarh

Eden Garden
declared completion Dec 2020 · M C Babu
Eden Garden
declared completion Dec 2019 · Laxmikantan R Venkatraman
Eden Garden II
declared completion Dec 2019 · M C Babu
Eden Garden Phase -II
declared completion Mar 2022 · Laxmikantan R Venkatraman
Eden Paradise
possession by Jul 2027 · M C Babu
Eden Park
declared completion Nov 2020 · Prominent Builders AND Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026