MahaRERA Property Intelligence · Mumbai Suburban

Eden II

P51800047320 · Vile Parle East · promoter Sambhavparshva Developers Pvt

Certificate SignedDue 31 Dec 2026

Delivery & Registration

MahaRERA registrationP51800047320
Registered on19 Oct 2022
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today5 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Sambhavparshva Developers Pvt is the promoter of record on 6 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9.

BuildingWingsFloorsDeclared completion
Eden II1G+9-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Vile Parle East, Junction of Ram Mandir Road and Prarthana Samaj Road, Ward GSouth, Mumbai City, 400057. Per the filed land record, the plot is bounded to the north by FP No - 95, to the south by FP No - 97, to the east by FP No - 107 and to the west by Ram Mandir Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Sambhavparshva Developers Pvt. Ltd. is the promoter on 4 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Sambhavparshva Developers Pvt. Ltd.

Sambhavparshva Developers Pvt. Ltd.
FlaggedMumbai Suburban
Sambhavparshva Developers Pvt. Ltd.
FlaggedMumbai City
Sambhavparshva Developers Pvt. Ltd.
FlaggedMumbai Suburban

Other RERA-registered projects in Vile Parle East

Vidyalankar Chsl
possession by Jul 2026 · Desai Residency Private Limited
Viva Dhanlaxmi
possession by Aug 2026 · Y K & Sons Mumbai
Parkway Manor
possession by Aug 2026 · Gautam Ekanath Thakur
Sandeep Ankur Residency
possession by Aug 2026 · Anusri Enterprises LLP
Moti Madhav
possession by Sep 2026 · Aadhya Skyvista
Neumec Niwara
possession by Sep 2026 · Neumec Venture

Major developers building in Vile Parle East

Other RERA-registered projects in Mumbai Suburban

Edenrose
possession by Mar 2027 · Hillview Venture
Edge
possession by Dec 2028 · Join Trak Infra Private Limited
Edifice
declared completion Dec 2017 · Buildpro
Edmont - Aurelia
possession by Aug 2029 · Sheth Homes Private Limited
EE Heights
declared completion Jun 2026 · Saadh Enterprise
Ekadanta
declared completion Dec 2022 · Anaaya Buildcon Constructions LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026