MahaRERA · the public record
EDGE
KHAR WEST · JOIN TRAK INFRA PRIVATE LIMITED
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
31 Dec 2028
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P51800066562
Delivery and registration
When is the project declared for completion?
EDGE is registered with MahaRERA as P51800066562 and the promoter has declared completion for 31 Dec 2028.
31 Dec 2028
declared completion
27months to go
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P51800066562 |
| Registered on | 11 Jun 2024 |
| Promoter-declared completion | 31 Dec 2028 |
| Current status | Certificate Signed |
| Against today | 27 months to the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for EDGE record 8 quarterly progress reports since registration.
8quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Filing progress reports — 8 quarterly progress reports on record since registration, with no current default.
Promoter record
What else is this promoter on record for?
Join Trak Infra is the promoter of record on 29 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
29projects
registered with MahaRERA
2flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Construction
How much construction cost has been reported?
In EDGE, ₹21.63 Cr of a declared ₹65.00 Cr estimated project cost is reported as incurred, about 33.3%, as at the last certified filing with MahaRERA.
33.3%
₹21.63 Cr
of ₹65.00 Cr declared cost
Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.
Source · MahaRERA quarterly progress filing · read 12 Jul 2026
Sales
How much has actually been sold?
In EDGE, 2 of 5 homes filed with MahaRERA are recorded as sold or booked, about 40%, and 3 remain available.
40%sold
2 of 5 homes
₹16.45 Cr
committed by buyers
Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹4.60 Cr (about 28%) is recorded as collected and ₹11.85 Cr as receivable. The project registers 37 homes in total, while this sold/unsold inventory filing covers 5 of them.
Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026
The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.
| Floor | Unit | Carpet | Govt reckoner value |
|---|---|---|---|
| Floor 11 | 1105 | 746 sqft (69.26 sqm) | ₹2.78 Cr |
| Floor 12 | 1203 | 1,263 sqft (117.35 sqm) | ₹4.71 Cr |
| Floor 12 | 1204 | 994 sqft (92.38 sqm) | ₹3.70 Cr |
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for EDGE in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 19 September 2026
What the filings record, home by home
Read from MahaRERA on 19 September 2026
MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 2 homes carry one, and 3 of the 5 are recorded unsold.
Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:
| Home | Carpet | Filed for the same home on other floors | Based on |
|---|---|---|---|
| 1105 | 746 sqft | Rs 5.9800 cr to Rs 10.4716 cr | 2 filed at this size |
A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13 and 37 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| EDGE | 1 | G+13 | 37 | - |
Unit mix on the filing: 37 residential.
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Legal & Litigation
The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.
| Court | Case no. | Year | Status |
|---|---|---|---|
| City Civil Court | 213 OF 2023 | 2023 | Closed |
Location, Land & Connectivity
Located at KHAR WEST, At Junction Of Ramakrishna Mission Marg & 15th Road, Khar (W), Andheri, Mumbai Suburban, 400052. Per the filed land record, the plot is bounded to the north by BY RAMKRISHNA MISSION MARG, to the south by CTS NO POINT E OBLIC 196 OBLIC A, to the east by BY 15TH ROAD and to the west by CTSNO POINT194 AND CTSNOPOINT 195 OBLIC A. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.
| Landmark | Straight-line |
|---|---|
| Chhatrapati Shivaji Int'l Airport | 4 km |
| Bandra Kurla Complex (BKC) | 4 km |
| Andheri MIDC / SEEPZ | 7 km |
| Lower Parel / Worli business district | 8 km |
| Powai / Hiranandani business park | 9 km |
| Nariman Point / Fort | 16 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.